Stage 2: Electrical and solar basics · topic 7 of 53

Hand tools, power tools and fixings

The right tool used the right way: torque wrenches, drilling and fixings, DC connector crimping, sealed roof penetrations, ladders and tool checks. You will know what to use, what to check first and when to reject a tool.

  • Core
  • Beginner
  • about 10 hours

Part of the Solar PV technician roadmap: from first safety to mid level

Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps

Every step with a tool has a source for its figure (the manufacturer’s manual for torque, the connector maker for the crimp, the fixing maker’s data for pull-out), a check before use and a record that you did it. That makes the tool part of the installation, not something you own. Practise on scrap in a workshop, never on a roof or on live equipment.

Reading the van before a one-day tiled-roof job

The job is a domestic one on a tiled roof with a masonry parapet. This is an invented scenario to show the decisions, not a site procedure. At the van, the findings and the decisions go like this:

  • Torque wrench with an out-of-date calibration label: it stays in the van and you use one that is in date, because the clamp figure in the manual is not negotiable.
  • Power tool with a cut in its lead: you tag it and take it out of service, because the PUWER regulations require work equipment to be suitable and maintained.
  • A general-purpose crimper in the bag, and connectors of one particular brand: you use the connector maker’s tool, or the connectors wait.
  • A parapet to drill: you check behind the surface for cables and pipes, fit the extractor and wear eye and breathing protection.
  • Modules to get up: they go on a ladder hoist, not on your shoulder, as set out in working at height and roof safety.

The cost of these checks is a short delay. Skipping them is how an untorqued clamp or a poor crimp ends up on a customer’s roof. The work that uses every tool above is in installing rails, hooks, flashings and modules and DC wiring, connectors and labelling.

When a colleague’s habit and the manual disagree

MIS 3002 says equipment should be installed in accordance with the manufacturer’s instructions, so the manual is the reference you can point to. If a colleague’s habit differs from it, follow the manual and ask your supervisor to settle the difference, so it is decided once and recorded, not argued on the roof.

What you will learn

  • How to use torque wrenches and drivers and where the torque figures come from
  • How to drill into timber, masonry and metal without damaging what is behind
  • Why DC connectors need the maker's crimping tool and how cable is stripped properly
  • How sealants and flashings keep a roof penetration watertight
  • How to choose, check and use ladders and hoists
  • How to inspect and look after tools, and how to control dust, noise and vibration

The parts of this topic

Torque wrenches and driversabout 1 hour

Tighten to the manufacturer's figure with a calibrated tool, then mark the fixing so it can be checked.

Clamps, rails, terminals and enclosure screws each have a torque figure in the manufacturer's instructions, and MIS 3002 says equipment should be installed in accordance with those instructions. Use a torque wrench or torque driver set to that figure, check its calibration date, and mark the fastener with a paint pen once done. Tightening by feel, or reusing a figure from a different product, defeats the check. Example: a clamp row checked and marked, then re-checked at the quality stage.

Drilling and fixings in timber, masonry and metalabout 1 hour

Choose the right bit and fixing for the material, check behind the surface first, and control the dust.

Timber, masonry and metal need different bits, speeds and fixings, and every fixing has a pull-out value in the manufacturer's data. Dust is not a nuisance: construction dust and crystalline silica from masonry and concrete cause serious lung disease, so control it at source. Check for hidden cables and pipes before you drill and wear the right eye and breathing protection. Drilling into a masonry parapet, for instance, goes with an extractor attached to the drill to catch the dust.

DC connector crimping and cable strippingabout 1 hour

Use the connector maker's crimp tool and procedure; a poor crimp is a classic cause of heat and failure in a string.

MIS 3002 requires DC connectors to be made up with the right tools and method, and its note says the wrong crimping tools have been a significant contributing factor in connection failures and even fires. A tool that fits but does not make a gas-tight crimp looks fine on day one and fails in a year. Strip to the stated length, crimp with the maker's tool, and check the pull on a sample. Match connector brands only when the maker says they are compatible.

Sealants, flashing and weathertightnessabout 1 hour

Every roof penetration must stay watertight; use the right flashing or seal and keep a photo record.

Hooks, brackets and cable entries pass through the roof covering, and each one must be sealed or flashed so water cannot get in. MIS 3002 says tiles or slates must be notched or flashed so gaps are not made larger than before, and that weathertightness should be maintained for the life of the system. Do not rely on sealant alone for a penetration the roofing trade would flash. A lead-flashed bracket on a tiled roof, photographed before the tile goes back, is one example.

Ladders and hoistsabout 1 hour

Choose, check and secure ladders properly, and lift modules with hoists rather than carrying them up a ladder.

HSE says ladders suit low-risk, short tasks, should be level, stable and secured, and checked before use; a ladder used for access should be tied off and rise at least 1 m past the step-off point. OSHA's solar guidance says workers should never climb ladders carrying solar panels and that ladder hoists, swing hoists or truck-mounted cranes or conveyors should be used wherever possible. Carrying a module up a ladder to save time is the shortcut to avoid. Example: a ladder hoist lifts modules to the eaves.

Tool care and inspectionabout 1 hour

Check leads, guards and calibration before each use; take faulty tools out of service and report them.

Before use, look at the lead, plug, casing, guard and switch of a power tool, and the calibration label on a torque or test tool. HSE guidance on maintaining portable electrical equipment explains that simple checks and, where needed, inspection and testing keep tools safe. A cut lead on a drill, for instance, means the drill is tagged and removed from the van. Take a faulty tool out of service even when the job is almost done: the PUWER regulations require work equipment to be suitable and maintained.

Dust, noise and vibrationabout 1 hour

Drilling and cutting create dust, noise and hand-arm vibration that harm health over time, so control them.

Regular drilling and cutting produce dust, noise and hand-arm vibration, which cause lung disease, hearing loss and nerve and circulation damage if uncontrolled. Harm builds up over years of daily exposure, so a single job can feel harmless. HSE's guidance covers how to assess and control each, for example using extraction, choosing quieter or lower-vibration tools and limiting exposure time. For a morning of masonry drilling, that can mean an extractor and hearing protection.

Practice task

On a practice board or scrap timber in a workshop (not on a roof, and not on live equipment), drill and fix three different fixings, tighten five bolts to a stated torque with a torque wrench and mark them with a paint pen, and strip and terminate five offcuts of cable using the correct tool. Photograph each result, and write a one-page tool checklist you would run through before starting a job, including what you would reject.

Skills you build

Torque toolsDrilling and fixingDC connector assemblyWeatherproof penetrationsLadder useTool inspection

Resources for this topic

Every source here is free. Each link opens the provider's own site in a new tab.

Back to the whole roadmap

Live jobs

Live Solar PV technician jobs

Roles whose title matches this career path.

All Renewable Energy jobs

Spot a problem with this topic?

Tell us what is wrong, missing or unclear here. Your note is attached to this topic.

Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.