Practical maths and units for solar
The calculations you will do every week: kW, kWh and kWp, chained percentage losses, roof slope, row spacing, voltage drop and a first yield estimate. You will be able to check a software figure by hand.
- Core
- Beginner
- about 12 hours
Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps
Units go beside every number, everything is converted first and rounding comes last. Then do the same job in a tool such as PVGIS and compare. If the two differ by a lot, find out why before the number goes into a quote.
The same roof, by hand and in PVGIS
A roof plane has room for 12 modules of 400 W each. The factors and the PVGIS result below are invented for the example, not real ones; use the real table for a real quote. Both routes use the same tilt and direction.
- By hand: 12 x 400 W = 4,800 W, which is 4.8 kWp after dividing by 1,000. Then 4.8 kWp x 900 kWh per kWp x 0.95 shading factor = 4,320 x 0.95 = 4,104 kWh a year.
- In PVGIS: 3,700 kWh a year.
The gap is 4,104 - 3,700 = 404 kWh, about 10 per cent of the hand figure (404 / 4,104 = 0.098). Before trusting either number, check the tilt and direction you each used, whether one method already includes a loss the other adds (so a loss is counted twice, or missed), and whether the factor in your table suits that location. If you cannot explain a gap like this, do not send the higher number. Quote the figure you can defend, as an estimate for the first year, not a guarantee. The full loss chain is in sizing, yield estimates and losses.
Checks before a figure leaves your desk
- The module count: did you use the sloped roof length or the plan length? On a 35 degree roof a 4.0 m run is 4.88 m of slope.
- The cable length: did you count the way back as well as the way out? The circuit relationships behind that sum are in DC and AC circuit fundamentals, and string, inverter and cable design covers a proper design.
- The unit on the label: is the figure in W or kW, and is it kWp or kWh? Convert both sides to one unit.
- The factor’s source and date: a table or tool you cannot name is a guess.
What you will learn
- The difference between kW, kWh and kWp, and how to convert between units without error
- How chained percentage losses combine, and why they do not simply add up
- Trigonometry for sloped roof lengths, tilt angles and row spacing
- How to estimate yearly energy from system size, a location factor and a shading factor
- How to calculate voltage drop in a cable as a number of volts and as a percentage
The parts of this topic
kW, kWh and kWpabout 2 hours
Power, energy and rated peak: three units that are easy to mix up and costly to get wrong.
kW is power at a moment, kWh is energy over time, and kWp is the system's rated peak: the sum of the module label watts at standard test conditions. Example: ten 400 W modules make a 4 kWp array; running at 2 kW for three hours makes 6 kWh. Quoting a system in kW when you mean kWp, or yield in kW when you mean kWh, is a common slip. Write the unit beside every number, and convert a datasheet figure and a bill figure to the same unit before comparing them.
Percentage lossesabout 2 hours
Losses multiply rather than add: ten 3 percent losses leave about 74 percent, not 70.
Each loss (temperature, soiling, wiring, inverter) takes a percentage of what is left, so you multiply the remaining fractions. Ten losses of 3 percent each leave 0.97 to the power ten, about 0.74 of the starting energy, a total loss of about 26 percent, not 30. Adding losses overstates the total, and so does counting one loss twice because two tools both include it. Performance ratio is the usual summary of this chain.
- PVPMC: PV performance metrics Sandia National Laboratories · Guide
- Solar photovoltaic performance and efficiency basics US Department of Energy · Guide
Unit conversionabout 2 hours
Convert millimetres, square metres, watts and kilowatts without slips; write the unit beside every number.
Most errors are unit errors. Millimetres become metres by dividing by 1,000, and areas need the factor squared: a module of 1,722 mm by 1,134 mm is about 1.95 square metres, not 1.95 million square millimetres in a spreadsheet cell you forgot to convert. Watts divide by 1,000 for kW. The SI system gives the standard prefixes and symbols. Never mix units mid-calculation: convert everything first, calculate, and only then round.
- SI units NIST · Guide
Trigonometry for tilt and row spacingabout 2 hours
Sine, cosine and tangent give sloped roof lengths, array heights and the spacing that avoids row-to-row shade.
On a pitched roof the slope length is the horizontal run divided by the cosine of the pitch: a 4.0 m run at 35 degrees is about 4.88 m of slope. On a flat roof a tilted row of height h casts a shadow of h divided by the tangent of the sun's elevation: a 1.7 m module at 15 degrees tilt stands about 0.44 m tall, and with the sun 15 degrees above the horizon its shadow is about 1.6 m. Use the sloped area, not the plan area, and a winter sun angle, not a summer one, for a shading check.
- Precalculus 2e, chapter 5: trigonometric functions OpenStax (Rice University) · Book
- PVPMC: fixed tilt Sandia National Laboratories · Guide
A simple yield estimateabout 2 hours
Yearly energy is roughly system size times a location factor times a shading factor, then checked against PVGIS.
MIS 3002 gives the UK method as annual output equals kWp times a regional kWh per kWp factor times a shading factor. Example with illustrative numbers: 4 kWp x 900 kWh/kWp x 0.95 = 3,420 kWh; use the real table for a real quote. PVGIS gives a second opinion from satellite data and lets you change tilt and losses. Quote the figure as an estimate, not a guarantee: the standard text itself says an estimate is guidance for the first year and not a guarantee.
- MIS 3002 Issue 6.0: the Solar PV Standard (Installation) MCS · Standard Free to read. Dated 18 March 2026; mandatory for contractors certified under it from 18 June 2026. The library also lists a redeveloped MIS 3002:2025 Issue 2.0, so check which one your employer is certified to.
- PVGIS 5 user manual European Commission Joint Research Centre · Guide
Cable arithmetic and voltage dropabout 2 hours
Voltage drop is current times resistance; work it in volts and as a percentage of the system voltage.
Copper's resistance is about 0.0172 ohm square millimetres per metre, so a cable's resistance is 0.0172 times the length (out and back) divided by its area. For 20 m of 4 mm squared cable, current travels out and back over 40 m, giving about 0.17 ohm; at 10 A the drop is about 1.7 V, which is 0.43 percent of 400 V. Count the return path, and do not treat the cable's current rating as if it fixed the voltage drop. Use the designer's table and local code.
- PVPMC: DC wiring losses Sandia National Laboratories · Guide
- PVPMC: AC wiring losses Sandia National Laboratories · Guide
- Wiring Unlimited: the book on cabling and DC systems (Victron Energy) Victron Energy · Book Written for battery and low-voltage DC systems; the cable, fuse and voltage-drop ideas apply, the numbers do not transfer to PV strings.
Practice task
Make a one-page workbook with five worked examples, each with units written out: a module count for a roof from measured dimensions, a system size in kWp, a chain of five losses combined into one figure, the slope length of a 35 degree roof from a 4 m run, and a yield estimate for a real address using PVGIS beside the hand method. End with a short note on which numbers you would double-check before putting them in a quote.
Skills you build
kW, kWh and kWpPercentage lossesUnit conversionTrigonometry for tilt and spacingSimple yield estimateCable arithmetic
Resources for this topic
Every source here is free. Each link opens the provider's own site in a new tab.
- Algebra and Trigonometry 2e, chapter 1: prerequisites OpenStax (Rice University) · Book
- Energy units and calculators explained US Energy Information Administration · Guide
- California C-46 Solar contractor exam study guide California Contractors State License Board · Guide Shows how one US state tests solar knowledge; California only.
- PVGIS: Photovoltaic Geographical Information System European Commission Joint Research Centre · Tool Free yield and irradiation tool; check its coverage map for your location.
- Introduction to Solar Photovoltaic (PV) Installation Southface Institute · Course Free, five modules, US-oriented.
Latest Renewable Energy jobs
No title matches the role right now, so these are the latest jobs in the same category.
No live jobs to show right now. Check back soon, or browse every green job.
Spot a problem with this topic?
Tell us what is wrong, missing or unclear here. Your note is attached to this topic.
Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.