Stage 5: Codes, standards and grid connection · topic 19 of 53

Your regional code track

Each region has its own rules on who may install solar PV, to which wiring code and under which grid rule. Pick yours, learn its documents and check each one is current.

  • Core
  • Intermediate
  • about 20 hours
  • Pick one

Part of the Solar PV technician roadmap: from first safety to mid level

Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps

Your region’s licensing line decides which documents you will use yourself and which belong to the electrician you work under, so settle it first. Then list the wiring code, the grid-connection rule, the equipment-listing rule and any scheme standard for your region. Next to each, write the current edition, who makes it binding and the date you checked.

A cheat-sheet row for Great Britain

Here is how a UK sheet could start, using only what this page’s sources say (as read on 20 November 2026; confirm each on the issuer’s site):

  • Wiring code: BS 7671:2018+A4:2026, Amendment 4 published 15 April 2026. Checked at: the IET press release and SELECT’s free summary.
  • Scheme standard: MIS 3002 issue 6.0, dated 18 March 2026, mandatory for certified contractors from 18 June 2026. It says BS 7671 prevails if the two conflict.
  • Grid rule: ENA G98 up to 16 A per phase, G99 above, G100 for export limiting (the notify-or-apply decision is in grid connection, metering and incentives).
  • Not confirmed: which MIS 3002 issue your employer’s certification follows.

Name the issue every time you quote a clause

The last row of that sheet matters in practice. The roof-structure check is clause 5.9.4 in issue 6.0 and clause 3.9.3 in the MIS 3002:2025 issue 2.0 (both read on 20 November 2026). A free guide that says “see 3.9.3” is not wrong, it is describing a different document. Name the issue every time.

The US row has an extra line: the edition adopted here

The NEC is revised every three years, but each state or city adopts an edition on its own schedule. Two jobs in the same month can sit under different editions: one under an authority on the 2020 edition and one on 2023. IAEI’s summary shows the rapid shutdown wording changed between those editions, so a layout checked against one edition must be checked again against the other. Ask the authority having jurisdiction which edition and which local amendments apply, and write the answer and the date on the sheet.

Free summaries help you see what changed, but read the text you are working to. MIS 3002 is free for personal use; NFPA 70 and 70E are paid. The international standards map shows which IEC numbers sit behind national ones.

Licensing comes from the regulator, not from a code

A code tells you how work is done, not who may do it. Take the licensing line from the regulator’s own text, and settle the route before the code: entry routes and licensing lays out the options.

Job adverts carry the licensing line too. Among the 17 postings in the sample (UK, US, Germany, India and Australia; how we research roadmaps), 12 wanted an electrical qualification or licence: all 4 UK, all 3 Indian, the 1 Australian, 3 of the 4 German and 1 of the 5 US postings. All 4 UK postings also named the 18th Edition (BS 7671).

This page tells you what to read. It does not authorise any work, and where it and your regulator disagree, the regulator wins.

What you will learn

  • The documents that make up the rulebook where you will work: wiring code, grid-connection rule, product-listing rule and any scheme standard
  • How to find the current edition and amendment of each, and who makes it binding: government, scheme or local authority
  • Which work needs a licence or a registered person, and what a trained assistant may do under supervision
  • How the grid-connection, array and labelling rules fit together on one job

Pick one of these

These are alternatives. Learn the one your employer or course uses; one is enough to complete the topic.

[UK] BS 7671, MIS 3002 and G98/G99about 20 hours

UK work sits on BS 7671:2018+A4:2026, the MCS standard MIS 3002 for systems up to 50 kWp, and the ENA grid rules G98, G99 and G100.

BS 7671 is the wiring code; Amendment 4 was published on 15 April 2026. MIS 3002 issue 6.0 covers MCS-certified systems up to 50 kWp DC, points to the IET Code of Practice and says BS 7671 prevails if they conflict. The ENA grid rules are G98 up to 16 A per phase, G99 above that, and G100 for export limiting. A separate MIS 3002:2025 issue 2.0 exists for the redeveloped MCS scheme and numbers its clauses differently, so ask which scheme your employer is certified under before you quote a clause.

[US] NEC, UL listings and NFPA 70Eabout 20 hours

US work follows the NEC edition your state or city has adopted, UL-listed equipment, and NFPA 70E and OSHA rules for electrical safety at work.

The NEC is revised on a three-year cycle, and each state or city adopts an edition on its own schedule, so ask the authority having jurisdiction which one applies. IAEI describes how rapid shutdown (690.12) changed across the 2014, 2017, 2020 and 2023 editions, and UL 3741 gives a listing route for PV hazard control systems. A guide written for an older edition can mislead on a job under the adopted one. NFPA 70 and 70E are paid standards.

[DE/EU] German rules and the EU pictureabout 20 hours

In Germany only the grid operator or a listed installation company may work on a connected installation, and a trade agreement lets an instructed person do DC cabling under an electrician.

Section 13 NAV says work on the customer installation may be done only by the grid operator or a company in the grid operator's installer register; maintenance is exempt except between the main fuse and the meter. A trade agreement describes an eight-teaching-unit course for an electrically instructed person (EuP) who may cable modules and lay string cables under an Elektrofachkraft, with connectors made while cables are de-energised. Live work and connecting to the installation are listed as not permitted. For other EU countries this page has no verified national text, so check yours.

[IN] CEA rules, IS codes and ALMMabout 20 hours

In India, check the CEA's connectivity rules, the IS and IEC standards named in scheme documents (such as IS 3043 earthing) and the ALMM list for modules.

The primary CEA, BIS and MNRE texts were not checked for this page, so read their current versions yourself. The UPNEDA primer for 3 kW rooftop vendors names IS 3043:2018 for earthing, IEC 62305 for lightning protection and IEC 62109 or IS 16221 for inverters. It expects each module to show its ALMM approval status and says the net meter is installed only by the distribution company (DISCOM). It is one state agency's document, not national law.

[AU] Wiring Rules and accreditationabout 20 hours

In Australia solar PV is licensed electrical work under the Wiring Rules (AS/NZS 3000), and small-scale solar accreditation is run by Solar Accreditation Australia.

The Victorian guideline of December 2018 says installing PV systems is electrical installation work for licensed electrical workers, and names AS/NZS 3000 (Wiring Rules) and AS/NZS 4836 for safe working near low-voltage installations. The Clean Energy Regulator says registered agents must check that installers and designers hold Solar Accreditation Australia accreditation and that components are Clean Energy Council approved. PV-specific standards exist, possibly AS/NZS 5033 and 4777, but this page did not verify them: confirm with Standards Australia. Rules differ by state.

Practice task

Choose your region and write a two-page cheat sheet: the documents that apply, the current edition of each and where and when you checked it, the three rules that most change what an installer does on site, and the work that needs a licence. Add one thing you could not confirm and who you would ask.

Skills you build

Finding the current edition of a codeNavigating a wiring codeGrid-connection rules for your regionKnowing which work needs a licence

Resources for this topic

Every source here is free. Each link opens the provider's own site in a new tab.

Back to the whole roadmap

Live jobs

Live Solar PV technician jobs

Roles whose title matches this career path.

All Renewable Energy jobs

Spot a problem with this topic?

Tell us what is wrong, missing or unclear here. Your note is attached to this topic.

Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.