Stage 5: Codes, standards and grid connection · topic 20 of 53

Grid connection, metering and incentives

Decide whether to notify the network operator or apply first, fit a generation meter that payment schemes accept, and see why incentives tie payment to certified installers.

  • Core
  • Intermediate
  • about 8 hours

Part of the Solar PV technician roadmap: from first safety to mid level

Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps

Add up the current per phase of every generator at the property before ordering anything. That one number picks the route (notify or apply), the lead time and sometimes the meter. Then settle who tells whom: the network operator, any payment scheme and the customer each need something different, and each has its own deadline.

Adding a battery to a house that already has PV

A customer had PV fitted two years ago and now wants a battery on the same single-phase supply. The ratings are made up, and the network operator’s page and the G98 or G99 text decide how to count.

The existing PV inverter is 2.8 kW and the new battery 3 kW, so together they are 2.8 + 3 = 5.8 kW. At 230 V that is 5,800 / 230 = about 25 A per phase. MIS 3002 says the 16 A per phase threshold is the total aggregated AC output of all generators, so 25 A means G99. Separately, SSEN says an installer must apply first if there is more than one generator at the property; ask the network operator whether a battery counts as a second generator, though the total already settles the route.

So the application goes in before anything is connected, and nobody can promise a switch-on date until the network operator replies. The PV alone was about 12 A (2,800 / 230), well under the line: the battery changed the route, not the roof. Commissioning, inverter set-up and first output covers the step after the connection is agreed.

What to tell the customer, and what not to promise

Say plainly which dates belong to someone else: G99 approval to the network operator, an Indian net meter to the DISCOM, export payments to a supplier. Give the customer a one-page timeline: when the form goes in, who replies, when the meter is read and who pays on what readings. Leave out a start date or a payment figure you do not control. What is handed over and registered afterwards is in the handover pack, certificates and registration.

The incentive rules move. Ofgem’s pages describe the Smart Export Guarantee, but whether MCS certification is a condition of it was not stated on the pages opened for this topic, so check before you say it to a customer.

The same question in other regions

India, the US and Germany ask it in other words: a DISCOM net-meter agreement, a utility interconnection application under NEC 705, a company on the grid operator’s installer register. Your regional code track says which text applies.

In several countries the connection step must be done or signed off by a licensed electrician or a listed company. Follow your local licensing rules.

What you will learn

  • The Great Britain split at 16 A per phase: G98 notification after commissioning, G99 application before connecting, and why storage counts towards the total
  • What type-test evidence the network operator expects for an inverter, and where it is looked up
  • What a generation meter is for, when a MID-approved meter is required, and what export limiting means
  • How incentives link payment to certified or registered installers: UK Smart Export Guarantee and MCS, Indian net metering, the German installer register
  • What to tell a customer, in plain words, about what happens between sign-off and the first payment

The parts of this topic

Notify or apply: the 16 A per phase lineabout 2 hours

In Great Britain, up to 16 A per phase is notified within 28 days of commissioning; above that, or in listed special cases, you apply before connecting.

The usual slip is sizing the PV under the limit and forgetting the battery: MIS 3002 says 16 A is the total of all generators, so 3 kW of PV and a 3 kW battery on one single-phase supply goes to G99. SSEN's page says the installer submits G98 Form B within 28 days of commissioning, but must apply first if there is more than one generator at the property, if the same installer fitted generation at another property with a closely matching postcode in the last 28 days, or if the site exceeds G98 limits.

Type-test evidence for invertersabout 1 hour

Network operators check inverter type-test evidence. The ENA register that held it has closed, and its own page says the data moved to Connect Direct.

G98 and G99 depend on equipment having been type tested. The ENA Generator Type Test Register page says it closed on 16 April 2024 and its data moved to Connect Direct. The 2021 ENWL slides show installers entering a manufacturer's reference number from the register on the notification form. Example: the reference number for the exact inverter model goes on the form. An older how-to guide may still name the old website, so check where your network operator now expects the evidence.

Export limitation and generation meteringabout 1 hour

G100 covers export limiting; MIS 3002 requires a way to record total AC generation, and a MID-approved meter where the reading is used for billing or payment.

Check that the meter is acceptable to the payment scheme, not only that it suits the customer's display. MIS 3002 issue 6.0 says G100 applies where export is limited, that a means of recording and displaying total AC generation must be installed, and that the meter must be MID-approved if used for billing or payment, with a serial number that can be photographed beside the reading. Energy taken from the grid to charge a battery must not corrupt the generation readings used for payment.

Incentives and certified installers (UK)about 1 hour

UK support schemes tie payment to certified installers and approved equipment; the Smart Export Guarantee is paid by suppliers on export meter readings.

Ofgem's SEG pages say licensed suppliers pay generators for exported electricity on actual meter readings, for solar PV up to 5 MW in Great Britain. NICEIC says its MCS assessment covers a named Technical Supervisor for each technology, and MIS 3002 requires the installer to register the system on the MCS Installation Database within 10 working days of commissioning. The Ofgem pages opened for this topic did not say whether MCS certification is a condition of the SEG, so check the current rules before you tell a customer.

[IN] DISCOM net meteringabout 1 hour

In India the DISCOM fits the net meter after the user submits an interconnection or net-metering agreement; state rules differ, so check yours.

The UPNEDA primer for 3 kW systems says a single-phase bidirectional meter is used and that the net meter is installed only by the DISCOM after the user submits the interconnection or net-metering agreement. It was written for Uttar Pradesh vendors under the PM Surya Ghar scheme. Other states and schemes differ, and the national scheme pages were not opened. Never promise the customer a start date before the DISCOM has fitted the meter.

[US] Interconnection and supply-side connectionsabout 1 hour

US systems need a utility interconnection application and a connection point that follows NEC article 705, supply side or load side, as set by the adopted edition.

The NABCEP guide's utility interconnection section explains that an inverter can connect on the load side or the supply side of the service disconnect, under different rules. IAEI says the 2023 NEC substantially rewrote 705.11 on supply-side connections. The guide is based on the 2014 NEC, so use it for the idea, then check the edition your jurisdiction has adopted and the utility's own application rules. No utility page was opened for this topic, and processes differ by state.

[DE] Installer register and plant registerabout 1 hour

In Germany, work on a connected installation needs a company on the grid operator's installer register, and plants are also entered in a national register.

NAV section 13 requires a company listed by the grid operator for work on the connected installation. The Federal Network Agency runs the Marktstammdatenregister, where a plant, its operator or another market actor can be registered. The page opened did not say which systems must be entered or whether it costs anything, so check the current duty before commissioning. Registration is a step separate from the grid operator, and easy to forget once the technical work is done.

Practice task

Take three paper scenarios: a 3.6 kW single-phase PV system; the same system plus a 5 kW battery on the same supply; and a 12 kW three-phase PV system. For each, work out the current per phase, decide whether G98 or G99 applies, list what the installer must send and when, and name the meter that records generation. Check each answer against the sources and note any case the sources do not settle.

Skills you build

Notify-or-apply decisionsGeneration and export meteringExport limitation awarenessIncentive eligibility

Resources for this topic

Every source here is free. Each link opens the provider's own site in a new tab.

Back to the whole roadmap

Live jobs

Latest Renewable Energy jobs

No title matches the role right now, so these are the latest jobs in the same category.

All Renewable Energy jobs

No live jobs to show right now. Check back soon, or browse every green job.

Spot a problem with this topic?

Tell us what is wrong, missing or unclear here. Your note is attached to this topic.

Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.