Permits, inspection and product listings
Know who has to approve a solar job, when the roof needs a structural check, and which listings make equipment acceptable to a scheme or an inspector.
- Core
- Intermediate
- about 6 hours
Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps
Four questions, asked in this order and each answered with its source, cover a permit sheet: who must be told, whether the roof can carry the array, whether the array changes how the roof behaves in a fire, and whether every product’s certificate covers the way you will use it. The order matters because an early “no” changes the design that the later questions are about.
A cut-roof house in England, answered four ways
A house in England has a traditional cut timber roof with a hip and a dormer valley. The rules cited are MIS 3002 issue 6.0; the house itself is invented. On a real job the survey supplies these facts, and site and roof survey covers what to record.
Who is told? The customer must be told who notifies building control (clause 5.1.6). If your firm is responsible, notification is complete before handover (5.1.7). Self-certification in place of building control is allowed only for a firm registered with an approved Competent Persons Scheme.
Can the roof carry it? A pitched roof needs a check by a suitably competent person (5.9.4). But Table 1 sends traditional cut roofs with hips or valleys to a structural engineer, and a dormer or valley is on the standard’s list of features that raise snow build-up. Here the answer is to call an engineer; mounting systems and roof structures covers what each roof type must carry.
What happens in a fire? The contractor must be able to show the modules have not affected the roof’s fire performance (5.8.1). One route in the note is mounting above an existing non-combustible covering. The gap under the panels is what the Building Safety Regulator research focuses on.
Does each certificate cover this use? The module and the kit must be certified to work together: a kit certified with named modules may be used only with those modules. Collect the certificate for each product and check the model matches.
Each answer goes on the permit-and-checks sheet with the clause or page beside it. If an answer is “ask the engineer”, the sheet says who asked and when. The records then close the job in the handover pack, certificates and registration.
Flat roofs and the date on the notice
The NFRC’s notice of 27 June 2025 on how clause 5.5.5 of MIS 3002 applied to flat-roof mounting products announced an extension that ran to 10 November 2025, so ask MCS or your employer what applies now. Whatever the kit, a ballasted flat roof needs a structural engineer to confirm the roof can take the array and the ballast.
Work only within your local licensing rules, and name the issue of any standard whose clause you quote: clause numbers change between issues.
What you will learn
- Who signs off a solar job in your region: building control or the authority having jurisdiction, a competent person scheme, or a certification body
- When a structural check is needed: a normal pitched roof checked by a competent person, and unusual roofs, shallow roofs and ballasted flat roofs sent to a structural engineer (MIS 3002 issue 6.0)
- Why an array can change how a roof behaves in a fire, and how the UK Building Safety Regulator research describes it
- How to check that modules, mounting kits and inverters carry the listing your region expects (MCS, UL, ALMM or BIS) and are used as listed
- Which records to keep so a roof warranty question or an inspection can be answered years later
The parts of this topic
Building control, competent persons and the AHJabout 1 hour
Find out who approves the work: in England building control or a competent person scheme, in the US the authority having jurisdiction.
Where work is notifiable under the Building Regulations, MIS 3002 issue 6.0 says the customer must be told who notifies, the installer must complete notification before handover if responsible, and self-certification in place of building control is allowed only when the work is done by a firm registered with an approved Competent Persons Scheme. In the US the AHJ plays a similar role. Never assume the customer or a landlord has already notified. Rules differ across the four UK nations.
- Find a competent person Front Door (LABC) · Tool Search tool for registered firms. The page does not explain electrical self-certification.
Structural check triggersabout 1 hour
MIS 3002 issue 6.0 wants a pitched roof checked by a suitably competent person and sends unusual roofs and ballasted systems to a structural engineer.
A roof counts as pitched under MIS 3002 issue 6.0 if it is over 10 and under 70 degrees. Clause 5.9.4 has a suitably competent person check the structure; clause 5.9.6 sends unusual roofs to a structural engineer: signs of distress, later modification, pitches under 30 degrees, or features that collect snow such as dormers, valleys and parapets. Ballasted flat roofs also need an engineer. Mounting kits outside MCS 012 need a structural assessment and wind-load calculation tied to the design. The standard does not say what the check must contain, so ask your employer for its method.
- What MIS 3002 actually requires and who it lets sign it off PBC Today · Guide Trade press summary, published September 2026. Check against the standard.
Roof fire performanceabout 1 hour
Research for the UK Building Safety Regulator found that a gap under panels can speed flame spread; MIS 3002 asks installers to show the array has not worsened the roof's fire performance.
The OFR Consultants report for the Building Safety Regulator (revision 02, 7 January 2026) reviews research showing that a panel above a roof covering can trap heat and speed flame spread, depending on gap height, and recommends non-combustible roof coverings beneath arrays and layouts that limit spread. A fire test of the roof covering alone does not tell you how the roof behaves with panels fitted, and MIS 3002 clause 5.8.1 expects the contractor to demonstrate that the installation has not affected the roof's fire performance.
- Thermal exposure to roofs from fires involving photovoltaic panels OFR Consultants for the Building Safety Regulator · Guide Long technical report; read the summary and recommendations.
Product listings: MCS, UL, ALMM and BISabout 2 hours
Check that modules, mounting kits and inverters carry the listing your scheme or region requires, and that the certificate matches the exact model and use.
Under MIS 3002 issue 6.0, modules must be certified to MCS 005 (or MCS 017) and listed on the MCS site, pitched-roof mounting products certified to MCS 012, and mounting parts approved to work together. A listed product used outside its listing loses the protection, for example another maker's module on a kit certified only for a named module. In India the UPNEDA primer expects each module to show its ALMM approval status. In the US, listing marks such as UL appear on equipment and inspectors may rely on them.
- MCS standards and tools library MCS · Standard Where the current issue of each MCS standard is published.
- Rooftop solar primer for vendors, 3 kW UPNEDA, Uttar Pradesh · Guide India. Shows what module markings and certificates are expected.
Manufacturer instructions, roof warranty and recordsabout 1 hour
Install to each manufacturer's instructions, check whether the roof's warranty is affected, and keep dated photos, calculations and certificates.
MIS 3002 says equipment should be installed to the manufacturer's instructions, that a roof warranty provider should be consulted where a warranty exists, and that if a warranty may be invalidated the customer must be told in writing and agree in writing; a clause in standard terms is not enough. Photographs and method statements can evidence that weather-tightness was maintained. Do not rely on memory: a dated photo of each fixing or flashing answers a roof claim years later.
- MIS 3002:2025 Issue 2.0, the redeveloped MCS installation standard MCS · Standard Free for personal use. A second issue exists for the redeveloped scheme; ask which one your employer is certified under.
Practice task
Take a pitched-roof job described in two paragraphs (house age, roof covering, pitch, array size) and fill in a permit-and-checks sheet: which approvals or notifications apply in your region, whether a structural engineer is needed and why, what the roof fire question is, and which listing evidence you would collect for each product. Mark each answer with the source you used.
Skills you build
Permit and notification routesStructural check triggersRoof fire performanceProduct listing checks
Resources for this topic
Every source here is free. Each link opens the provider's own site in a new tab.
- Approved Document P: electrical safety in dwellings (England) GOV.UK · Law or regulation Explains when electrical work must be notified. Check the nation you work in: Scotland, Wales and Northern Ireland differ.
- Approved Document B: fire safety (England) GOV.UK · Law or regulation Two volumes, dwellings and other buildings. MIS 3002 refers to it for roof fire classification.
- MIS 3002 Issue 6.0, sections 5.1, 5.5, 5.8 and 5.9 MCS · Standard Free for personal use. Covers notification, equipment listing, roof fire performance and structural checks.
- NABCEP PV Installation Professional Resource Guide NABCEP · Guide US view of permitting, listing marks and inspection. 2016 edition, based on the 2014 NEC.
- Extension for the use of flat roof solar mounting products NFRC · Guide Notice dated 27 June 2025 on how clause 5.5.5 of MIS 3002 applied to flat roofs. The extension it announces ran to 10 November 2025, which has passed, so check the current position.
Live Solar PV technician jobs
Roles whose title matches this career path.
Spot a problem with this topic?
Tell us what is wrong, missing or unclear here. Your note is attached to this topic.
Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.