Stage 8: Testing, commissioning and handover · topic 32 of 53

Inspection and tests before switch-on

These are the checks that show a PV system is safe to energise: inspection, earthing, polarity, string voltage and current, insulation resistance and AC tests. You will be able to read the record and spot a result that means stop.

  • Core
  • Intermediate
  • about 14 hours

Part of the Solar PV technician roadmap: from first safety to mid level

Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps

Order matters in pre-switch-on testing: inspect against the design, fix what the inspection finds, isolate and prove dead where the circuit can be made dead, test, then write each result from the instrument. A lit string cannot be made dead by isolating it from the inverter, because DC cables can stay live with the power off, so Voc and Isc readings are live measurements. Skipping ahead is how a damaged connector becomes a hazard during a test. The method and pass values come from the current standard and your supervisor, not from this page.

String 2 reads 440 V: what now?

All the figures in this record are invented. The designer’s expected open-circuit voltage is 480 V for each string (12 modules × 40 V from the datasheet). Both strings were read within minutes of each other, at the same recorded irradiance: string 1 reads 478 V and string 2 reads 440 V.

  • String 1 is close to expected. Record it as read, with the instrument named.
  • String 2 is 40 V short (480 - 440), about 8% below expected. Do not round, average or re-measure until it looks better. How close counts as close enough comes from the standard and your supervisor.
  • What it means is for the qualified person to find with the string isolated. One low reading does not name the cause.
  • Do not energise. Tell the person responsible, and record the re-test after the fault is fixed.

The AC side has its own record

The same sheet cannot cover the AC side. MIS 3002 points to separate IEC 60364-6 inspection and test report references for it. IEC 62446-1 and the IET Code of Practice set out the test methods, and both are paid documents this page does not draw on. After a pass, the next step is commissioning, inverter set-up and first output.

Who tests, and which qualifications employers ask for

Of the 4 UK postings in our sample of 17 (UK, US, Germany, India and Australia; how we research roadmaps), 2 asked for the 2391 inspection and testing qualification. Plan your own route with certifications and licences by region. Before any of this, test instruments and safe testing covers choosing and proving the instrument, and lockout/tagout and permits to work covers keeping the system isolated.

Only an authorised, trained person performs these tests on a real system. The practice task here is a form exercise from sample data.

What you will learn

  • What the inspection checks before any test: the install against the design, the manufacturer's instructions and the labelling.
  • What each PV test proves: earthing and bonding continuity, polarity, string open-circuit voltage, string short-circuit current and array insulation resistance.
  • Why string readings are compared with each other and with the datasheet, allowing for irradiance and temperature.
  • Which AC tests apply under your local code, and who carries them out.
  • How to fill in and read a test record such as the MCS array test report, and what to do when a result is out of range.
  • Why the current standard, not this page, gives the test method and pass values, and why only authorised people test.

The parts of this topic

Visual inspection before testingabout 2 hours

Inspect the installation against the design and the instructions before any test: ratings, wiring, labels, earthing, connectors and fixings.

The NABCEP guide lists what a pre-operation inspection checks: circuit voltages and currents, conductor and overcurrent device sizes, disconnecting means, wiring methods and connectors, grounding, markings and labels, and connections to other sources. It recommends an inspection checklist, and a final punch list that includes verifying disconnects are open and lockout is in place. Photograph defects. Do not skip the inspection because the test will find it: a loose or damaged part can make a test unsafe.

Earthing and bonding continuityabout 2 hours

Check that the earthing and bonding of frames, rails and equipment is continuous and as designed. The standards say what resistance and method apply.

MIS 3002 Appendix E's array test report has a line for earth continuity "where fitted", which reflects that frame earthing is a design decision that must be recorded. IEC 62548-1's scope includes earthing provisions for the DC side. The method and limits come from the standard and your supervisor, not from this page. Record the instrument and the result. If earthing was not fitted, write why on that line rather than leaving it blank.

Polarity, string Voc and Iscabout 3 hours

Open-circuit voltage and short-circuit current per string show whether modules are connected right and working. Compare strings with each other and with the datasheet.

The MCS array test report records, per string, the expected and measured Voc and Isc, the irradiance and a polarity check. PVPMC explains that a failed connector or blown fuse can create an open circuit and that in a module with three bypass diodes, an open-circuit cell or a shorted diode reduces output by a third. A string that reads far from its siblings points to a fault. Example: the form has an irradiance field because a reading in weak light is not comparable with a datasheet value at standard test conditions.

DC insulation resistanceabout 3 hours

The insulation test checks for leakage from array wiring and modules to earth. It is done only by an authorised person with the array isolated and prepared.

MIS 3002's array test report records the test voltage and the positive-to-earth and negative-to-earth results for each string. The Victorian guideline says to isolate and lock out before work, and warns that solar DC cables can remain live with the power off. The NABCEP guide describes the preparation of the array for the test. These are steps for an authorised person following the current standard. Before trusting any reading, confirm the array really was isolated.

AC tests under local codeabout 2 hours

The AC side is inspected and tested like any electrical installation, to the wiring code of the country, by a qualified electrician.

MIS 3002 says the system shall be inspected and tested in accordance with Section 16 of the IET Code of Practice for grid-connected PV (except 16.4), a paid document this page does not draw on, and its forms refer to IEC 60364-6 inspection and test report references. SELECT's summary of Amendment 4 notes little change to Part 6 but a new requirement for an EICR to follow the model in Appendix 6 on periodic inspection. The DC test sheet does not cover the AC side.

Test records and failed testsabout 2 hours

Fill in the record from the instrument, not the design, and treat an out-of-range result as a stop sign: report it, do not energise, and do not 'try again until it passes'.

A failed result means a fault to find and fix, then a documented re-test; repeating a test until a number looks acceptable, instead of finding the cause, is the habit to avoid. HSE's GS38 says testing should be done dead where possible, and INDG354 gives guidance to people managing or carrying out electrical testing. Write the result, the instrument and the date, and tell the person responsible.

Practice task

Using the layout of the MIS 3002 Appendix E array test report, fill in a record for a fictional two-string system from a real module datasheet (Voc and Isc at standard test conditions), including irradiance and test voltage fields. Then change one string's Voc by about 15% and one insulation reading to a very low value, and write what each result might mean, which standard you would look to for the limit, and who you would tell. This is a desk exercise: do not measure any real system.

Skills you build

Visual inspectionReading PV test recordsInterpreting Voc, Isc and insulation resultsEscalating a failed test

Resources for this topic

Every source here is free. Each link opens the provider's own site in a new tab.

Back to the whole roadmap

Live jobs

Latest Renewable Energy jobs

No title matches the role right now, so these are the latest jobs in the same category.

All Renewable Energy jobs

No live jobs to show right now. Check back soon, or browse every green job.

Spot a problem with this topic?

Tell us what is wrong, missing or unclear here. Your note is attached to this topic.

Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.