Stage 8: Testing, commissioning and handover · topic 33 of 53

Commissioning, inverter set-up and first output

Commissioning turns a built system into a working one. You will be able to say which settings and functional checks follow the tests, how to judge first output against sunlight, and what to notify and show the customer.

  • Core
  • Intermediate
  • about 12 hours

Part of the Solar PV technician roadmap: from first safety to mid level

Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps

Once an authorised person has confirmed the pre-switch-on results, the order is: check the inverter’s settings against its manual and the network operator’s rules, run the functional checks the manual lists, compare the first output with the sunlight, then notify the network operator (some systems must apply before connecting) and walk the customer through shutdown. Each step leaves a written record, because those records are the baseline for every later visit.

What 2.4 kW and 1.6 kW say about a 4 kWp system

All the numbers here are made up. A 4 kWp system (4 kW of DC rating at standard test conditions) is running at 2 pm, and a reference cell or pyranometer reads 800 W/m2 in the plane of the array. The design estimate’s performance ratio is taken as 0.80; take the real one from your own design.

PVPMC says performance ratio can be evaluated hourly or over other intervals, so as a rough check the expected output is 4 kW × (800 ÷ 1,000) × 0.80 = 2.56 kW.

If the inverter shows 2.4 kW, that is 2.4 ÷ 2.56 = 94% of expected. How close counts as close enough is for the design estimate and your supervisor to say. Log the date, irradiance, module temperature and output as the baseline that monitoring and performance analysis builds on.

If it shows 1.6 kW, that is 1.6 ÷ 2.56 = 63%. Check the cheap explanations first. Is the sensor clean and in the plane of the array? Is it thin cloud, or early or late in the day? Is a power or export limit set, from a default or a mistake? Only then does it become a question about the strings, and that goes to the electrician.

Who notifies and who sets the inverter

In Great Britain, MIS 3002 clause 5.1.9 makes the MCS contractor responsible for notifying the network operator, so whoever commissions needs the right form and the deadline: see grid connection, metering and incentives.

Inverter configuration, monitoring or SCADA skills were asked for in 6 of the 17 postings in our sample (UK, US, Germany, India and Australia; how we research roadmaps), and commissioning technician is a job title in its own right.

Energising a system and changing AC-side settings is for an authorised person. Your part is to prepare the script, assist and check, and the paperwork then follows in handover pack, certificates and registration.

What you will learn

  • Why the inverter's country or grid-code setting must match the network and be recorded.
  • How export limits, voltage management devices and the arc-fault function are handled and recorded (MIS 3002: arc-fault function enabled where present).
  • What anti-islanding means and why a functional loss-of-grid check is part of commissioning.
  • How monitoring, passwords and customer alerts are set up with the customer's agreement.
  • How to judge first output against irradiance and expectation, and log a baseline.
  • How the network notification, the shutdown procedure and the labels close the job.

The parts of this topic

Grid profile and country settingabout 2 hours

Inverters carry a country or grid-code setting chosen at commissioning. Choose the one the network requires and record it; a wrong one can put the system outside its type-test evidence.

Network operators rely on type-test evidence for the inverter, and SSEN's page says applications need an Inverter Type Test Certificate whose power rating matches the inverter on the schematic. The settings used at commissioning should be those the evidence and the network operator's rules cover; the manual names the profile for each country. The ENA type-test register page says the register closed in April 2024. Check the profile rather than assuming the factory default is right.

Export limit, voltage management and arc-fault settingsabout 2 hours

Set and record export limits, and keep any arc-fault function in the inverter enabled. MIS 3002 also bars connecting PV to a voltage management device without the network operator's consent.

MIS 3002 issue 6.0 says G100 applies where export is limited, that any arc-fault detection function in the inverter shall be enabled, and that PV shall not be connected to the AC output of any form of voltage management device without the network operator's consent. Advanced inverter functions such as power limiting and voltage control sit in the settings menu. Nuisance alarms can tempt someone to switch a protective function off; find the cause instead.

Anti-islanding and the loss-of-grid checkabout 2 hours

A grid-connected inverter must stop feeding a dead network quickly and wait before reconnecting. The commissioning functional test shows it does.

PVPMC says grid-connected inverters should sense a loss of grid and disconnect quickly so the PV system does not keep powering an isolated network, citing 2 seconds for disconnection and a 5-minute wait before reconnecting in IEEE 1547 and IEC 62116, with similar trips for out-of-range voltage or frequency. Follow the manual's functional test, done by the authorised person. A feature listed on the datasheet is not proof that it works on this site.

  • PVPMC: loss of grid Sandia National Laboratories · Guide Why inverters disconnect on loss of grid, and the reconnection delay.

Monitoring, credentials and customer alertsabout 2 hours

Set up the monitoring portal with the customer, change default passwords with them and make sure they will hear about a fault within the time the standard expects.

On monitoring, MIS 3002 says the customer should be notified within 48 hours of the system stopping or operating abnormally, that network credentials for internet-connected devices must be updated in consultation with the customer, and that components should meet ETSI TS 103 645 where they are connected. Register the portal in the customer's name where possible and write down who has access. Example: the installer's own email left as the only alert contact.

First output versus irradianceabout 2 hours

Compare the first output with what the sunlight and the estimate predict, and log the readings as a baseline. A big gap points to a fault, a shade or a wrong setting.

Output judged at dawn or under thin cloud tells you little, so for a first check use an irradiance reading, the module temperature and the inverter's output, and compare with the estimate. PVPMC defines performance ratio as AC yield divided by the reference yield from plane-of-array insolation, and notes it reads lower in warm periods. Log the date, irradiance and output as a baseline: tests at commissioning are the reference for later visits.

  • PVPMC: performance ratio Sandia National Laboratories · Guide Definition and limits of the performance ratio.
  • PVGIS user manual European Commission Joint Research Centre · Guide What the estimate you compare against is made of.

Notification, shutdown procedure and labelsabout 2 hours

Send the network notification or confirm approval, show the shutdown procedure and check the labels. In Great Britain the G98 form follows within 28 days.

SSEN's page says the G98 Form B goes to the network operator within 28 days of commissioning, and the ENWL slides show the installer completing it and entering the inverter's manufacturer reference. The NABCEP guide lists demonstrating and verifying shutdown and emergency procedures and user training as commissioning steps. Leave the shutdown guide where the customer or a responder will find it. Notify within the 28 days, and check you are using the current form version.

Practice task

Write a one-page commissioning script for a domestic inverter from its free installation manual: the settings to check (country profile, export limit, arc-fault function, monitoring), the functional tests the manual lists, an "expected versus actual output" box using a PVGIS figure or a measured irradiance, the notification to send and when, and the point where you stop and call the electrician. Mark clearly which steps only an authorised electrician performs.

Skills you build

Inverter set-upFunctional testingOutput versus irradiance checkCustomer shutdown instructions

Resources for this topic

Every source here is free. Each link opens the provider's own site in a new tab.

Back to the whole roadmap

Live jobs

Latest Renewable Energy jobs

No title matches the role right now, so these are the latest jobs in the same category.

All Renewable Energy jobs

No live jobs to show right now. Check back soon, or browse every green job.

Spot a problem with this topic?

Tell us what is wrong, missing or unclear here. Your note is attached to this topic.

Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.