Stage 3: Safety first (do not skip) · topic 9 of 53

Lockout/tagout and permits to work

How lockout/tagout and permits to work keep equipment from restarting while someone works on it. You will know who is authorised, what a lock and tag record, and why a battery needs its own plan.

  • Core
  • Beginner
  • about 6 hours

Part of the Solar PV technician roadmap: from first safety to mid level

Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps

Who isolated it, and who may restore it? A lock answers that for one named person, and a permit answers it for a whole site. Both also answer which energy sources exist and who is working. Your employer’s procedure sets the real rules, and you will be trained on it; learn the logic here so that the procedure makes sense when you meet it, starting from electrical safety for DC and AC solar work.

A shared hasp on one inverter block, from permit to handback

This is an invented walk-through to show the logic, not a procedure for a real site. A large solar plant has several inverter blocks, and one needs work while the rest keep running.

A permit to work names the job, the block, the people, the hazards and the isolations, and sets a time window. The isolating point carries a shared hasp, and each of the three authorised technicians adds a personal lock. The operations desk and a crew working nearby are affected people, so they are told. The plant also has a battery container, which appears on the permit as its own source with its own isolation, because isolating the inverter does not de-energise it. Batteries have their own topic, battery storage fundamentals.

Then the day gets complicated. One technician breaks for lunch: her lock stays on. Another finishes early and removes his own lock and only his. A third is sent home unwell with her lock still on the hasp. Nobody simply cuts it off. The rule is that the person who applied a lock removes it. OSHA allows narrow exceptions, but only after the employer has confirmed the owner is not on site and only if the owner is told before returning to work, so the supervisor follows the employer’s procedure. Power returns only at handback: every lock off, the permit closed and everyone confirmed clear.

How the US and British systems word the same idea

In the US, OSHA’s rules (1910.147 and 1910.333) speak of locks, tags, authorised and affected employees. In Britain, HSE’s guidance (HSG85 on safe working practices and HSG250 on permit-to-work systems) speaks of isolation and permits. The words differ, but the logic is the same: identify every source, isolate, verify, record, hand back. HSG250 was written for process industries, so treat it as a model for large shared sites rather than as the rule for a house roof. Which wording governs your work depends on your country and your employer’s procedure. Routine maintenance visits are in O&M programmes and inspection routines.

What you will learn

  • What hazardous energy is and why solar equipment has several sources of it
  • The lock, tag, verify and restore sequence in outline
  • Who is an authorised person and who is an affected person
  • How permits to work and group lockout control shared work
  • Why batteries and capacitors need stored-energy checks
  • How US lockout/tagout rules and UK and EU permit systems differ

The parts of this topic

Lock, tag, verify and restoreabout 1 hour

Isolate every source, lock and tag it, verify the state, work, then restore only when everyone is clear.

OSHA's solar page lists the core steps: identify and isolate all energy sources, lock or tag the isolating device in the safe position, release stored energy, and verify isolation before work. Locks and tags identify the worker who applied them and stay until the work is finished. 'Switched off' is not the end of the job: the verify step is what makes the isolation real. Example: an inverter isolator locked off with a personal lock and a tag showing the owner.

Authorised people, affected people and group lockoutabout 1 hour

Qualified people verify and test the isolation; affected people must be told; groups use a shared point with personal locks.

OSHA's general-industry rule 1910.333 says circuits must be locked out or tagged, that a qualified person verifies the equipment cannot be restarted and tests that the circuit parts are de-energised, and that each lock and tag is removed by the employee who applied it, with narrow exceptions. The lockout standard 1910.147 (linked above) adds that affected employees, such as colleagues who use the equipment or work nearby, must be notified, and that in group lockout each authorised person adds a personal lock. With three technicians, each adds a personal lock to the same hasp. Your lock stays on until your own part is done; stepping away without it 'for a minute' defeats the system.

Permits to workabout 1 hour

A written permit says what work, where, who, for how long and what isolations are in place; it stops at handback.

A permit to work is a formal written record that a defined job may go ahead, with the isolations, hazards, precautions and the people named, and a formal handback when it ends. A permit for work on one inverter block while the rest of the plant runs shows the idea. Treat the permit as the control it is, not as paperwork. HSE's guidance HSG250 was written for process industries, but the logic carries over to a large solar site where several contractors share a plant.

Stored energy in batteries and capacitorsabout 1 hour

Batteries and capacitors keep energy after isolation, so a battery system stays dangerous when everything else is off.

The Victorian guideline warns that battery cells can deliver a severe electric shock when connected as banks, and that there are 230 V AC parts as well, so energy storage is a serious risk if wrongly installed. Isolating the inverter does not de-energise a battery, and following the PV isolation routine while forgetting the battery is the classic gap. A home battery has its own isolator and a shutdown procedure that the manufacturer's manual describes step by step.

Circuits that cannot be isolatedabout 1 hour

When something must stay live nearby, the rule is to guard it or keep clear; only qualified people go near it.

Some circuits cannot be isolated, such as a supply cable you must work beside. OSHA 1926.416 says no employer may allow an employee to work so close to an electric power circuit that they could contact it, unless they are protected by de-energising and grounding it or by guarding it effectively with insulation or other means. Deciding it is fine because you will be careful is not a control: the guarding must be in place before work. Temporary insulating covers fitted by a qualified person over a live service are one form of guarding.

Practice task

Write a one-page lockout/tagout and permit plan for a fictional site with a grid supply, a DC array and a battery. Show each energy source, the isolation point, who is authorised to lock it, what the tag says, how stored energy is checked, who may remove each lock and what has to be confirmed before anyone restores power. Ask a qualified electrician or tutor to review it.

Skills you build

Lockout/tagout conceptsPermit to work awarenessStored-energy awarenessAuthorised and affected people

Resources for this topic

Every source here is free. Each link opens the provider's own site in a new tab.

Back to the whole roadmap

Live jobs

Latest Renewable Energy jobs

No title matches the role right now, so these are the latest jobs in the same category.

All Renewable Energy jobs

No live jobs to show right now. Check back soon, or browse every green job.

Spot a problem with this topic?

Tell us what is wrong, missing or unclear here. Your note is attached to this topic.

Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.