Mounting systems and roof structures
Rails, hooks, ballast and piles, and what the structure must carry: loads, roof coverings, tested kits and when an engineer is needed. You will sort a roof into 'check it' or 'ask an engineer'.
- Core
- Beginner
- about 10 hours
Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps
Before looking at rails and clamps, ask what carries the load: rafters, deck or soil. Then ask what the load is (modules, ballast, wind uplift, snow), and last how the roof stays weathertight and keeps its fire performance. Structural decisions belong to a competent person or an engineer, so a technician’s job is to know which question to ask and to stop when the answer is unclear.
Which of these three roofs needs an engineer?
MIS 3002 (Issue 6.0) sorts pitched roofs, those between 10 and 70 degrees, with a table of typical roof types. Some types have set calculation methods; others say to consult a structural engineer. The three roofs below are invented, to show the sorting.
A semi with timber trussed rafters, 35 degrees and no signs of trouble, is a typical type with a given method. A suitably competent person checks that the roof can carry the system (clause 5.9.4), and the layout fixes hooks to the rafters.
An older house with a traditional cut roof and a valley goes the other way: the table sends cut roofs with hips or valleys to a structural engineer.
A bungalow at 25 degrees with notched rafters meets two items on the standard’s “unusual roof” list: post-construction modification such as notching, and a pitch below 30 degrees. Where a roof is unusual or there is any doubt, a qualified structural engineer shall be consulted (5.9.6).
Nobody should settle these by eye. At the survey, photograph the rafters, note the pitch and any dormers, valleys or parapets, which raise snow build-up, and pass the facts to the person who decides: see site and roof survey. Whatever the answer, the edge rule applies: modules should not sit within 400 mm of a domestic roof edge unless measures resist the extra wind uplift (5.9.7). Access to the roof for any of it is covered in working at height and roof safety, and the installation itself in installing rails, hooks, flashings and modules.
Reading the right issue of MIS 3002
MCS’s library lists Issue 6.0 of MIS 3002 and a redeveloped MIS 3002:2025 Issue 2.0, both dated 18 March 2026, and trade press describes a March 2026 update affecting mounting. Clause numbers differ: the roof-structure check is 5.9.4 in one and 3.9.3 in the other. The trade-press summary says an engineer is not needed in the ordinary case, only for unusual roofs and ballasted systems, but Table 1 in Issue 6.0 also sends cut roofs with hips or valleys, and asymmetric duo-pitched roofs, to an engineer. Read the text, not a summary, and read the issue your employer’s certification body works to, as at 20 November 2026.
What to photograph and file
MIS 3002 says the roof warranty provider should be consulted where a warranty exists, and the customer told in writing, and agreeing explicitly, if it could be invalidated (5.9.2, 5.9.3). For non-MCS 012 systems it lists photographic records among the ways to show weathertightness (5.5.5). So photograph each penetration and keep the warranty check on file. The listing and sign-off side is in permits, inspection and product listings.
What you will learn
- The main mounting types: pitched roof hooks and rails, in-roof kits, flat-roof ballast, ground piles, carports and trackers
- Why loads (dead load, wind uplift, snow) decide the fixings and the layout
- How roof coverings are protected and kept weathertight
- What tested mounting kits are, including MCS 012 in the UK
- When a competent person or a structural engineer must check the structure
- Why there is doubt about which issue of the UK standard applies, and what to do about it
The parts of this topic
Pitched roof hooks and railsabout 1 hour
Hooks or brackets fix to the rafters, rails sit across them and clamps hold the modules, with tiles notched or flashed.
MIS 3002 defines pitched roofs as those between 10 and 70 degrees and says tiles or slates must be notched or flashed so gaps are no bigger than before. It also says modules should not sit within 400 mm of a domestic roof edge unless measures resist the extra wind uplift, and that fixing to metal cladding needs a check of sheet thickness and of the fixings back to the structure. Fix where the structure is, not where it looks neat: hooks, for example, are located on the rafters from a survey photo.
- MIS 3002 Issue 6.0: the Solar PV Standard (Installation) MCS · Standard Free to read. Dated 18 March 2026; mandatory for contractors certified under it from 18 June 2026. The library also lists a redeveloped MIS 3002:2025 Issue 2.0, so check which one your employer is certified to.
In-roof kitsabout 1 hour
In-roof systems replace the covering and so must carry the roof's weather and fire performance.
An in-roof system forms the main roof covering, so it must keep the roof watertight and meet the fire performance required for its position. Treat it as part of the roof covering, not as an ordinary above-roof system. MIS 3002 says an in-roof kit with the right fire rating can be used to show the fire performance of the roof has not been affected, and gives a worked example based on Approved Document B for England and Wales. An example is a kit with tested flashings and a declared fire class.
- Fire safety: Approved Document B GOV.UK · Law or regulation
Flat roofs and ballastabout 1 hour
Flat-roof arrays are held by weights, fixings or both; the roof must carry the load and the waterproofing must be protected.
Flat roofs, MIS 3002 says, are those under 10 degrees. Ballasted systems take wind pressure from recognised data such as BRE Digest 489 or specific test data, need a protection or slip layer compatible with the waterproofing, and use a friction coefficient of 0.3 unless tested. Ballast is a calculation, not just a matter of adding weights: a qualified structural engineer is consulted to check the roof can carry the system and the ballast. Example: a kerb or tether that stops sliding on gravel.
- Structure: Approved Document A GOV.UK · Law or regulation
Ground mounts, piles and ground screwsabout 1 hour
Ground arrays are carried by piles, ground screws or ballast foundations chosen from soil and load data.
Ground-mount arrays sit on fixed-tilt frames carried by driven piles, ground screws or concrete or ballast foundations, chosen from soil data and load calculations. Unknown ground can mean failed foundations, or needless over-design, so soil data is not optional. The Sandia guide describes how fixed-tilt arrays are modelled, and OSHA's solar guidance covers crane and hoist safety for lifting heavy components. A small farm array on driven piles might get a pull-out test before the full build.
- PVPMC: fixed tilt Sandia National Laboratories · Guide
- Solar energy: crane and hoist safety OSHA (United States) · Guide
Carports and trackersabout 1 hour
Carports and trackers are structures first and PV second; trackers add moving parts and wind-stow rules.
A solar carport is a building structure carrying modules, so it needs structural design, foundations and often planning permission. Trackers rotate the array to follow the sun: the US Department of Energy describes one-axis and two-axis trackers and notes that they add upfront cost and maintenance, and the Sandia guide explains how a tracked array's orientation changes with time. A tracker is not a fixed frame: moving parts need maintenance and safe-work rules. A single-axis tracker row adds a controller and a wind stow position.
- PVPMC: array orientation Sandia National Laboratories · Guide
Wind and snow loadsabout 1 hour
Loads decide fixings and spacing; designers use manufacturer tools, standards or an engineer, not guesswork.
Wind lifts and drags arrays and snow adds weight, so each fixing and each roof is checked against the loads for its location, height and edge zone, and last job's layout must not be reused on a different roof: loads change with every site. MIS 3002 cites Eurocode 1 for snow load in its roof methods and BRE Digest 489 for wind on roof-based PV; both are sold documents. Example: a manufacturer's software tool giving the number of hooks per module for a postcode and roof height.
Roof coverings and weathertightnessabout 1 hour
Every penetration must stay watertight, and an existing roof warranty may be affected by the installation.
MIS 3002 says PV systems should not adversely affect the weathertightness or structural integrity of the building, that the roof warranty provider should be consulted where a warranty exists, and that the customer must be told in writing, and agree explicitly, if the warranty could be invalidated. One example of following that is a recorded warranty check before the install. A clause in the contractor's terms and conditions does not meet a requirement for explicit agreement. Approved Document C covers resistance to moisture in England.
- Site preparation and resistance to contaminants and moisture: Approved Document C GOV.UK · Law or regulation
- NFRC: the UK roofing federation NFRC (UK) · Community Roofing trade body; a starting point for roofing standards and training in the UK.
MCS 012 tested kits (UK)about 1 hour
UK pitched-roof systems should use mounting kits tested and certified to MCS 012, with set exceptions.
MIS 3002 requires systems fixed above or built into pitched roofs to use kits tested and certified to MCS 012 (Pitched Roof Installation Kits), and all mounting parts to be approved to work together unless the maker calls them universally compatible. Where a kit is listed with named modules, only those modules may be used, so do not substitute parts. Where no certified kit suits, a non-MCS 012 system can be used with evidence of a structural and wind assessment, of how fire spread is minimised and of weathertightness.
- MIS 3002:2025 Issue 2.0 (redeveloped MCS scheme) MCS · Standard The MCS 012 clause is 3.5.2 in this issue (5.5.2 in Issue 6.0); the exception for other mounting systems is 3.5.5.
When a structural engineer is requiredabout 1 hour
Unusual or doubtful roofs, shallow pitches, signs of distress or heavy snow build-up call for an engineer, not a rule of thumb.
MIS 3002 says the roof structure must be checked by a suitably competent person, that typical roof types have set calculation methods, and that where the roof is unusual or there is any doubt a qualified structural engineer shall be consulted. Unusual includes signs of distress, post-construction modification, a pitch below 30 degrees or features that raise snow build-up. A trade-press article on Issue 6.0 says an engineer is not needed in the ordinary case, only for unusual roofs and ballasted systems, so read the current text. Example: an old terrace with notched rafters sent to an engineer. When in doubt, ask; do not guess.
- What MIS 3002 actually requires, and who it lets sign it off Planning, Building & Construction Today · Guide Trade-press summary of the newer MIS 3002 issue; read the standard itself, as clause numbers differ between issues.
Practice task
Choose a real pitched-roof mounting system whose installation manual is public. Using the manual and the MIS 3002 clauses on roofs, write a two-page worksheet: the parts list, the fixing positions relative to rafters, the edge-zone rule, the torque and sealing steps, what could go wrong on an old roof, and the points where you would stop and ask a structural engineer. Do not install anything; this is a desk exercise.
Skills you build
Mounting system typesRoof structure awarenessWind and snow load awarenessWeathertightnessTested mounting kits
Resources for this topic
Every source here is free. Each link opens the provider's own site in a new tab.
- MCS standards and tools library MCS · Standard Lists the current scheme documents, including MIS 3002.
- Solar photovoltaic system design basics US Department of Energy · Guide
- Approved Documents (building regulations, England) GOV.UK · Law or regulation
Live Solar PV technician jobs
Roles whose title matches this career path.
Spot a problem with this topic?
Tell us what is wrong, missing or unclear here. Your note is attached to this topic.
Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.