Stage 6: Survey, sizing and basic design · topic 22 of 53

Site and roof survey

A solar survey records what the design and the safety plan depend on: shade, roof structure, hazards, access, the electrical supply and how the customer uses power.

  • Core
  • Intermediate
  • about 12 hours

Part of the Solar PV technician roadmap: from first safety to mid level

Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps

Satellite imagery gives orientation and rough pitch, a sun-path tool gives the hours of any shade, and the customer’s bills give usage: that is the desk pass. The visit that follows is planned around what the desk could not answer: shade, the structure under the covering, hazards and the supply. HSE says to treat every roof as fragile until a competent person confirms otherwise, so the visit follows your employer’s risk assessment (working at height and roof safety sets the rules) and nobody climbs on an assumption.

A house that looked easy from above

A semi-detached house has a south-facing rear roof that looks clear of shade in satellite imagery. None of this is a real house: the findings show how a survey sheet changes the job.

  • Old corrugated sheets of unknown material on the single-storey extension, found before anyone climbs: the form says “material unknown, possible asbestos, not walked on, not touched”. HSE’s asbestos pages are the pointer for what happens next, and the array is planned on the main roof only. The access and hazard notes become the plan in job planning and access.
  • A neighbour’s tree that was bare in the imagery, seen in leaf from the garden: a sun-path tool shows it blocks the low afternoon sun in winter. The sketch marks the modules it would hit, and the designer applies a shade factor below 1 in the sizing and yield estimate.
  • One rafter in the loft, notched by a previous owner: MIS 3002 issue 6.0 lists post-construction modification such as notching as a sign of an unusual structure, so the roof goes to an engineer, not a quick check. The checks that follow are in permits, inspection and product listings.
  • A photo of the board showing no spare way, and a customer who mentions a battery next year: both go on the form, because a battery can change the grid-connection route.

Our sample (UK, US, Germany, India and Australia; how we research roadmaps) also holds 2 UK surveyor postings, read separately, and both asked for MCS knowledge, so MIS 3002 and its Appendix B are worth reading before your first survey.

Write down what you could not see

Anything you did not see goes on the form as “not seen”, never as a blank: the loft of a flat-roofed extension, the far side of a hip, a locked meter cupboard. A blank reads like an all-clear to the next person. “Not seen” tells the designer to ask. Give every measurement a unit and every photo a date, so someone who was not there can use them.

Do the practice task from your desk. Roof work and electrical inspection belong to trained, authorised people working within local licensing rules.

What you will learn

  • Measure or confirm orientation, tilt and shading, and see why the MCS method says an accurate shade estimate typically needs a site visit
  • Record roof structure, covering and condition so the structural check can be done, and note any sign of distress or past modification
  • Spot hazards before anyone climbs: asbestos, fragile surfaces, overhead lines, limited access and the need for scaffold
  • Record the electrical supply: meter and consumer unit position, single or three-phase, existing generation, and where the inverter and cables could go
  • Capture the customer's usage pattern and expectations, with a photo record another person can use

The parts of this topic

Orientation, tilt and shadingabout 3 hours

Inclination, orientation and shading are the three main site factors for output; maps and photos give the first two, but shade usually needs a site visit.

MIS 3002 Appendix B treats inclination, orientation and shading as the three site factors that matter most for output, and says drawings, maps or photos suit the first two while an accurate shade estimate will typically need a site visit. Remote imagery alone cannot show trees in leaf, aerials or a neighbour's planned extension. A chimney, for instance, can shade the lower corner of an array at mid-afternoon in winter. Use a sun-path tool to see which hours an object blocks the sun.

Roof structure, covering and conditionabout 2 hours

Record rafter or truss type, covering, pitch and any sign of distress, so a competent person or engineer can check the roof can carry the array.

MIS 3002 issue 6.0 requires the roof structure to be checked by a suitably competent person (clause 5.9.4) and sends unusual structures to an engineer (5.9.6): signs of structural distress, post-construction changes such as notched or removed timbers, shallow pitches under 30 degrees, or features that collect snow such as dormers, valleys and parapets. A record of the covering alone leaves the structural check with nothing to work from, so photograph the loft or roof underside as well as the outside.

Hazards: asbestos, fragile surfaces and overhead linesabout 2 hours

List what could hurt someone before anyone climbs: asbestos, fragile sheets and rooflights, overhead lines, roof cavity heat and sharp objects.

HSE says to treat every roof as fragile until a competent person confirms otherwise. Its asbestos hub points to typical locations and to task sheets for trades. The Victorian regulator's guideline adds that a roof-space risk assessment should look for heat, poor lighting, vermin, sharp objects and asbestos-containing materials. Write hazards on the survey form, not in your head: the form feeds the risk assessment and method statement.

Access and scaffold needabout 1 hour

Decide how people and modules get onto the roof: scaffold, ladder or hoist. HSE and Victorian guidance treat a ladder as a short-task option, not the default.

HSE says sloping roofs need scaffolding or edge protection at the eaves, and its ladder pages say a ladder can suit low-risk, short-duration tasks but should not automatically be the first choice. The Victorian guideline says a ladder should extend 900 mm above the step-off point, sit at about 4:1 and be secured, and should not be used to lift bulky items such as modules. Note on the survey where scaffold could stand and what ground it needs.

Meter, consumer unit and supplyabout 1 hour

Record single or three-phase supply, main fuse, board space, existing generation and cable routes. In Great Britain the notify-or-apply decision depends on them.

A photo of the meter by itself is not enough: SELECT's summary says Amendment 4 redrafted section 551 on generating sets, so the electrician needs a photo of the board and a note of its spare capacity. SSEN's page shows the connection route depends on total generation per phase, other generators at the property and recent nearby installs by the same installer, so the survey must record any existing generation and planned storage.

Photos and drone useabout 1 hour

A dated photo set lets the designer, roofer and electrician work without a second visit. Drone rules vary by country; check yours before flying.

Take photos of each roof face, eaves, ridge, loft structure, consumer unit, meter, inverter location, access route and any hazard, with a scale object where you can. Drones can speed up large roofs but need registration or permission in many countries. The UK CAA drone hub lists registration and Flyer ID, and complex commercial work needs further authorisation. Check your own country's aviation authority before flying.

Customer usage and expectationsabout 2 hours

Ask when the household or business uses power and why they want solar. Usage drives self-consumption and sizing more than roof area does.

MIS 3002 requires a self-consumption estimate based on an occupancy pattern (home all day, home half the day or out all day) and annual consumption, and says the figure is not a guarantee. The NABCEP guide shows electric bills reviewed during a survey. Ask about future changes: an EV, a heat pump, a home office. Quoting a generation figure invites the customer to assume it equals savings, so say what share they would use themselves.

Practice task

Survey a house on paper. Use a free satellite or street-view image and a sun-path tool to record orientation, tilt, shade objects and the sun path for your own home or a sample address, then produce a one-page survey form with a sketch, measurements, a hazard list and the photos you would need on site. Do not climb on any roof for this task.

Skills you build

Roof measurementShade assessmentHazard spottingPhoto and survey records

Resources for this topic

Every source here is free. Each link opens the provider's own site in a new tab.

Back to the whole roadmap

Live jobs

Live Solar PV technician jobs

Roles whose title matches this career path.

All Renewable Energy jobs

Spot a problem with this topic?

Tell us what is wrong, missing or unclear here. Your note is attached to this topic.

Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.