Job planning, access and logistics
Plan the day so it is safe and nothing is missing: check parts against the drawing, brief the crew, arrange access and deliveries, and agree when weather stops work.
- Core
- Intermediate
- about 8 hours
Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps
What stops the job, who is authorised for each task, and how do people and modules get up and down? Answer those before anything else, then check the parts list against the drawing. Anything you cannot answer two days ahead becomes a risk on the day, when the crew is waiting and the pressure to improvise is highest.
A terraced house, planned two days ahead
Ten modules in two strings of five are going on the rear roof of a terraced house, and the only way to the back is through the house. The house is made up; this is a planning method, not a site procedure.
The layout shows two strings, so string cable and connector counts must cover two. The order form lists connectors for one. Found on Thursday, that is a phone call. Found on the roof on Friday, it is a lost day.
Access comes next. The Victorian guideline says ladders should not be used for bulky items such as modules, so with no side access the plan needs scaffold with a hoist or other lifting aid, booked in time, and a route worked out through the hall.
Agree the weather rule with the supervisor before the day, in terms the crew can check: the forecast, a wet or frosty slope, an approaching storm. The limit is the supervisor’s call, not a number this page can set. Then put who does what on the brief sheet by name: roof fixings, DC cabling by those allowed to do it, AC connection by the qualified electrician, testing last.
If the roof cannot be finished in a day
A job rarely ends exactly on time. Before the first module goes up, write down what “safe to stop” means: what is secured, what is covered, and who makes sure access is closed. Ask your supervisor for the company’s routine, because it depends on the roof and the kit.
Heights and driving in the job ads
Employers in our sample (UK, US, Germany, India and Australia; how we research roadmaps) asked for a driving licence in 13 of 17 postings and for work at height or roof work in 11.
The plan builds on the site and roof survey and sits under the rules in working at height and roof safety and manual handling, RAMS and site safety. The day it plans is installing rails, hooks, flashings and modules.
Planning who may do which task, such as the AC connection, follows your region’s law. Work within your local licensing rules.
What you will learn
- Read the layout, single-line diagram and bill of materials, and check them against the survey before the day
- Run a pre-start briefing covering tasks, hazards, who is authorised to do which task, the emergency plan and the isolation arrangements
- Plan access: scaffold, ladders or hoist, how modules and tools reach the roof, and how to keep people out of the area below
- Plan deliveries, storage, weather limits for stopping work (wind, rain, frost, heat) and what is done if the roof cannot be finished in a day
- Coordinate roofer, electrician and customer so each knows when they are needed and what they must not do
The parts of this topic
Reading plans and the bill of materialsabout 2 hours
Check module count, string layout, cable lengths and every fixing and flashing against the drawing before loading the van. A missing part stops a roof job halfway.
Trust the drawing over the order form, or you may find the missing flashing on the roof: tick the bill of materials against the layout line by line (modules, rails, hooks or in-roof kit, flashings, clamps, cable, connectors, ties, glands, labels). A layout with 10 modules in two strings, for instance, needs the string cable and connector count to match. The UPNEDA 3 kW primer is a worked example of a bill of materials down to connector counts and cable ties.
- Rooftop solar primer for vendors, 3 kW UPNEDA, Uttar Pradesh · Guide India. Example bill of materials with quantities.
- NABCEP PV Installation Professional Resource Guide, chapter 3 NABCEP · Guide Managing the project. 2016 edition.
The pre-start briefabout 2 hours
A short meeting before work starts covering the tasks, hazards, who does what, isolation, emergency plan and stop-work triggers. Record who attended.
MIS 3002 issue 6.0 requires suitable and sufficient risk assessments before any work on site starts (clause 5.1.5). The Victorian guideline says a risk assessment should be done for each task, at the start of each day and at each change of task, and that a safe work method statement is required for high-risk work such as falls over 2 m or work near energised installations. Cover isolation, who is authorised for electrical tasks, first aid and emergency access. Make it about this roof and these people, not a generic sheet.
- Risk assessment: HSE overview HSE (UK) · Guide Identify the hazards, judge likelihood and seriousness, then control the risk.
Access, scaffold and hoistingabout 2 hours
Choose how people and modules reach the roof. A ladder suits short light tasks; it is not the way to carry modules, and the area below needs protecting.
HSE's ladder page says ladders can suit low-risk, short-duration tasks but should not automatically be first choice. The Victorian guideline says ladders should not be used where large, heavy or bulky items such as modules must be lifted, and sets a ladder at about 4:1, secured, and 900 mm above the step-off. Plan scaffold, a hoist or a lifting aid, and keep people clear below. Decide this before the day, not on it.
- Safe use of ladders and stepladders: HSE HSE (UK) · Guide Overview page; subpages cover choosing and securing a ladder.
- Falling Off Ladders Can Kill: Use Them Safely (OSHA 3625) US Department of Labor, OSHA · Guide English and Spanish. Starts with when a ladder is the right equipment.
Deliveries, storage and weather limitsabout 1 hour
Plan where pallets go, who unloads them and when the roof stops being safe to work on. Wind, wet and frost make roofs slippery and modules hard to hold.
Modules and rails need a storage place decided in advance (flat, off the ground, out of the weather), along with who unloads them with what, and the conditions at which roof work stops. HSE's roof-work page says roof work must be planned for safety; the Victorian guideline treats heat-related illness as a hazard to plan for, and a German sample work instruction says assembly must stop when thunderstorms or severe weather approach. A plan that works only in good weather is not a plan.
- Roof work: HSE guidance for construction HSE (UK) · Guide Planning, safe access, roof edges and fragile surfaces.
Roofer, electrician and customer coordinationabout 1 hour
Roof fixing and electrical connection can belong to different people. Agree the order, who may touch what, and what the customer must keep clear.
MIS 3002's note on risk assessment says PV combines electric shock, falls and awkward handling, which roofers and electricians each know only in part. Agree the sequence: roof fixings first, DC cabling by those allowed to do it, AC connection by the qualified electrician, testing last. Tell the customer what to move, where the supply will be off and for how long. Plan against two trades each assuming the other has made the roof or the supply safe.
- MIS 3002:2025 Issue 2.0, the redeveloped MCS installation standard MCS · Standard Free for personal use. Repeats the risk-assessment note in section 3.1.
Practice task
Write a one-page job plan for a sample 4.5 kWp pitched-roof installation: a bill-of-materials check against a layout drawing, a delivery and hoisting plan, a weather rule that says when work stops, a task list stating who may do each task under your region's rules, and a short pre-start briefing script. Review it with a supervisor or trained peer before treating it as finished.
Skills you build
Reading plans and bills of materialsPre-start briefingAccess and hoisting planningCoordinating trades
Resources for this topic
Every source here is free. Each link opens the provider's own site in a new tab.
- Work at Height Regulations 2005: the law HSE (UK) · Law or regulation Work must be planned, supervised and done by competent people with the right equipment.
- Working safely when installing PV systems (Victoria) Energy Safe Victoria and WorkSafe Victoria · Guide Dated December 2018. Risk assessments, safe work method statements and fall controls for installers.
- MIS 3002 Issue 6.0, sections 5.1.5 and 5.6 MCS · Standard Free for personal use. Requires risk assessments before any work starts.
- Protecting Roofing Workers (OSHA 3755) US Department of Labor, OSHA · Guide US. Fall protection, ladders, scaffolds, lifts and electrical safety for roofing work.
Latest Renewable Energy jobs
No title matches the role right now, so these are the latest jobs in the same category.
No live jobs to show right now. Check back soon, or browse every green job.
Spot a problem with this topic?
Tell us what is wrong, missing or unclear here. Your note is attached to this topic.
Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.