AC side, inverter and consumer unit tie-in
The AC side connects a solar inverter to the building's mains, and it is licensed or qualified work. You will understand it well enough to prepare it, check it and question it, and you will know where your own role stops.
- Core
- Intermediate
- about 16 hours
Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps
Inverter current decides which grid rules apply, and the cable run decides whether the inverter will trip. After those two numbers come the questions: where is the connection point, and which edition of the wiring code allows it? These are questions for the electrician, not a job to do. The work is licensed or qualified in the UK, Germany, India and Australia, and licensing varies by US state. Nothing here is permission to connect or test.
Current and voltage drop before the board
These are illustrative numbers on an assumed 230 V single-phase supply, with MIS 3002 issue 6.0 as read on 20 November 2026. The electrician’s design decides everything real. The inverter is the 3.6 kW one from the practice task.
The inverter alone: 3,600 W ÷ 230 V = about 15.7 A. MIS 3002 clause 5.1.8 points to G98 up to and including 16 A per phase (16 × 230 = 3,680 W), so this inverter sits just under the line.
With a 3 kW battery on the same supply: the total is 3,600 + 3,000 = 6,600 W, or 6,600 ÷ 230 = about 28.7 A. MIS 3002’s note to clause 5.1.9 says the 16 A threshold counts the combined output of all generators, so G99 would apply.
Voltage drop: 1% of 230 V is 2.3 V. Divided by 15.7 A, the line and neutral conductors together may have about 0.15 ohm (2.3 ÷ 15.7). Where MIS 3002’s note allows up to 3% for a long run, it is 6.9 V and about 0.44 ohm. Whether a given cable and length meet that comes from the cable maker’s resistance figures, which is the electrician’s calculation.
The connection point depends on the code edition
Both main codes were reworked recently. SELECT’s summary says BS 7671 Amendment 4 redrafted section 551 on generating sets, and IAEI says NEC 705.11 on supply-side connections was substantially rewritten in the 2023 edition. A board layout that was right last year may be wrong now, so the electrician works from the edition in force where the job is. See inverters and optimisers for what the inverter needs, and cables, protection and earthing for what the connection must carry.
How far your role goes
Of the 17 postings we sampled (UK, US, Germany, India and Australia; how we research roadmaps), 12 asked for an electrical trade qualification or licence: every UK, India and Australia posting, 3 of 4 in Germany and 1 of 5 in the US. State licensing varies in the US, so check your own state’s rules before assuming a job lets you connect. If you are not the authorised electrician, the safe default is to prepare, label, photograph and ask, and to leave connecting, isolating and testing the AC supply to the person who is. Entry routes and who may do which work covers your region.
What you will learn
- Where an inverter may and may not go: ventilation, temperature, ingress protection and access, always following the manufacturer's manual.
- How AC cable size, voltage drop and protective devices are chosen, including the MIS 3002 voltage-drop targets.
- How a PV circuit connects to a consumer unit or main board, and why BS 7671 Amendment 4 and NEC article 705 recently reworked the rules on where a generator may connect.
- Why AC-side earthing and bonding follow the design and the code, and who tests them.
- How generation meters, current clamps and communications are fitted and secured, including changing default network passwords with the customer.
- Where your own role stops: connection and sign-off belong to the licensed or qualified person in your region.
The parts of this topic
Inverter location, ventilation and ingress protectionabout 2 hours
Choose a place the manufacturer allows: ventilated, within temperature limits, with the right IP rating and reachable for service. Overheating makes an inverter limit its output.
MIS 3002 says the appropriate IP rating must be kept for the location. PVPMC says some inverters limit power when the cabinet overheats, with causes including failed cooling, clogged filters, high ambient temperature and installation problems. An inverter in a sunlit loft with no airflow, for instance, loses output on the best days. Check the manual for clearances, mounting surface and orientation: the spot nearest the board is convenient, but only the manual says whether it is allowed.
- PVPMC: inverter saturation or clipping Sandia National Laboratories · Guide Includes thermal limiting of inverters.
AC cable, voltage drop and protective devicesabout 3 hours
The AC cable and its overcurrent and RCD protection are chosen from the inverter's output, the run length and the wiring code. A high voltage drop can trip the inverter.
Sizing a cable for current alone can still fail on a long run. MIS 3002 issue 6.0 says AC cables shall be sized to minimise voltage drop as far as is reasonably practicable, measured from the supplier's cut-out to the inverter's AC terminals. A note says about 1% is practicable for most domestic work and up to 3% for larger systems or long runs, to cut losses and avoid nuisance over-voltage trips. The wiring code sets cable and protection rules, and the electrician, not the assistant, selects and signs them.
- PVPMC: AC wiring losses Sandia National Laboratories · Guide Usually small in homes, larger in big plants.
[UK] Board tie-in and BS 7671 Amendment 4about 3 hours
Amendment 4 redrafted BS 7671 section 551 on generating sets, which affects how and where a PV or battery circuit may connect to a board.
Choosing the connection is a decision for a qualified electrician, and last year's board layout is not a safe default. SELECT's free summary says Amendment 4 redrafted section 551. It adds a requirement for a suitable protective device where energy flow can be bidirectional, prohibits connecting a source on the load side of an RCD under certain conditions, and treats stationary batteries as generating sets, not loads, for the supply-side rule. Read the amendment itself before relying on this summary.
- BS 7671:2018+A4:2026, what's new (SELECT overview) SELECT · Guide Free summary. See the section 551 pages; the contents list shows no change to section 712.
- IET and BSI publish Amendment 4:2026 (press release) IET · Guide The 15 January 2026 announcement that the content was signed off. The SELECT overview gives the 15 April 2026 publication date.
[US] Supply-side and load-side connections (NEC 705)about 3 hours
In the US a PV inverter may connect on the load side or the supply side of the service disconnect, each with its own rules in NEC article 705.
The NABCEP guide's utility interconnection section explains that interactive inverters may connect on the load side or the supply side of the service disconnecting means, with different rules for each, and that supply-side connections are common when load-side rules cannot be met. IAEI says 705.11 was substantially rewritten in the 2023 NEC. The NABCEP guide is based on the 2014 NEC, so confirm the edition your area has adopted. Only a licensed person makes the connection.
- NABCEP PV Installation Professional Resource Guide, section 4.5 NABCEP · Guide 2016 edition. Section 4.5 covers utility interconnection.
Earthing and bonding of the AC sideabout 2 hours
AC earthing and bonding follow the design and the code of the country; the electrician tests them. Standards name the earthing and surge methods expected.
Earthing added on site with no design behind it, such as an earth rod or bonding conductor, is the case to avoid: add earthing only where the design says why. The UPNEDA primer names IS 3043:2018 as the code of practice for earthing, IEC 62305 for lightning protection and IEC 61643-11 for surge protection devices in India. The UK relies on BS 7671, and MIS 3002 asks for a recorded decision on frame earthing. Tests of earthing and bonding are part of the pre-energisation tests.
- Rooftop solar primer for vendors, 3 kW UPNEDA, Uttar Pradesh · Guide India. Lists earthing, lightning and surge standards for a small system.
Meters, current clamps and communicationsabout 2 hours
A generation meter should be fitted where the customer can read it, and any internet-connected device needs its default credentials changed with the customer.
MIS 3002 says the generation meter should be readable without a tool, ladder or torch, that a means of telling the customer within 48 hours if the system stops or misbehaves should be provided, and that device network credentials must be updated in consultation with the customer. Connected components should meet ETSI TS 103 645, and commercial premises need the IT owner's permission. Example: the installer's default password left on a customer's home network.
- MIS 3002:2025 Issue 2.0, section 3.7 MCS · Standard Free for personal use. Metering, data, communication and security clauses.
Where your role stops: licensingabout 1 hour
In most regions the AC connection must be done or signed off by a licensed electrician or a listed company. Know the line and stay behind it.
A short solar course does not change who may make the connection. Section 13 NAV says work to build, extend or change an installation behind the house connection fuse may be done only by the grid operator or a company on a grid operator's installer register (maintenance is partly exempt). The Clean Energy Council says solar installation in Australia is performed by a licensed electrician and that an accredited installer must first be a qualified electrician. The Victorian guideline says installing PV is licensed electrical work there.
- Section 13 of the NAV (low-voltage connection ordinance) Federal Ministry of Justice (Germany) · Law or regulation In German. Who may work on a connected installation.
- Small-scale solar careers Clean Energy Council · Guide Australia. Says installation is performed by a licensed electrician and that accredited installers must first be qualified electricians.
Practice task
On paper, prepare an AC-side connection plan for a 3.6 kW single-phase inverter in a house: a sketch of the board and the proposed point of connection, the cable run with voltage drop from the supply cut-out to the inverter against the MIS 3002 target, the protective devices you would expect, meter and communications placement, and a list of questions the electrician must settle before work starts. Mark every item "for the electrician to confirm". Do not open a consumer unit or touch any real installation.
Skills you build
Inverter sitingAC cable and voltage-drop checksReading a board tie-in planMetering and communications
Resources for this topic
Every source here is free. Each link opens the provider's own site in a new tab.
- MIS 3002 Issue 6.0, clauses 5.6.5 to 5.6.8 and section 5.7 MCS · Standard Free for personal use. Ingress protection, voltage management devices, arc-fault function, AC cable voltage drop, metering and communications.
- 2023 National Electrical Code and photovoltaic power systems IAEI Magazine · Guide US. Notes the substantial rewrite of NEC 705.11 on supply-side connections.
- Working safely when installing PV systems (Victoria) Energy Safe Victoria and WorkSafe Victoria · Guide Dated December 2018. Says PV installation is licensed electrical work in Victoria and describes isolation before work.
Latest Renewable Energy jobs
No title matches the role right now, so these are the latest jobs in the same category.
No live jobs to show right now. Check back soon, or browse every green job.
Spot a problem with this topic?
Tell us what is wrong, missing or unclear here. Your note is attached to this topic.
Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.