EV chargers, diverters and smart tariffs
The add-ons employers pair with solar: EV chargers, surplus diverters, load management, tariffs and grid-controlled devices. You will be able to explain how they share one supply and one day's sunshine.
- Optional
- Intermediate
- about 10 hours
Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps
These add-ons compete for two limited things: the supply’s capacity and the day’s solar surplus. Something has to decide who gets the power and when. Charger levels, diverters, load management, tariffs and grid control are different ways of making that decision, and this topic is a map of them, not a wiring guide.
What happens in one house at noon and in the evening?
A house has solar, a battery, a 7 kW EV charger, a 3 kW heat pump and a 3 kW oven, and its supply can carry 12 kW. The house and every figure in it are made up, and this is not a design.
What happens in the evening? Charger, heat pump and oven together draw 7 + 3 + 3 = 13 kW, which is over the 12 kW limit. A load manager cuts the charger to 6 kW while the oven runs: 6 + 3 + 3 = 12 kW. Without one, the main fuse may end up making the decision.
And at noon? If the roof exports 4 kW of surplus (also made up), the battery, a hot-water cylinder on a diverter and the car can all take it. If nothing sets an order, they compete. Choose a priority, such as cylinder first, then battery, then car, and write it into the settings and the handover. Battery storage fundamentals covers the battery side. The practice task asks you to draw this flow for a fictional home.
Quote payback with the tariff in front of you
A payback sum should show its arithmetic and say what happens if the rate moves. Work it twice, once at today’s tariff and once at a lower rate, and quote both so the customer sees the range. System types and metering covers how export is measured.
Who does the electrical work, and why this topic is optional
Fitting a charger or a heat-pump circuit is electrical work for a qualified, authorised person under local codes, and the settings come from the maker’s manual. Grid-control rules, such as Germany’s section 14a, are local and change, so read the current text; grid connection and incentives covers notification rules.
The topic is optional because many solar roles never touch it: 2 of the 17 job postings in our sample (UK, US, Germany, India and Australia; how we research roadmaps) asked for EV charger, heat pump or smart-meter work, and both were among the 4 German postings.
What you will learn
- How home EV charging is arranged and why it counts as a continuous load.
- How surplus diverters and energy management systems share solar between charger, heater, heat pump and battery.
- How load management stops a charger overloading a supply.
- How an export scheme and time-of-use tariffs change the sums for a customer.
- What grid-controlled devices are, using Germany's section 14a as a worked example.
The parts of this topic
Charger levels and home installationabout 2 hours
Home charging runs from a standard outlet or a dedicated higher-power circuit, installed to local codes by a qualified electrician.
The US Department of Energy page says Level 1 charging uses a standard outlet and Level 2 uses 240 V equipment; it recommends safety-certified equipment, says a qualified electrician can check a home's capacity and add circuits, notes that permits may be needed, and says the NEC treats EV charging as a continuous load, with Article 625 holding most of the charging-equipment rules. In practice an electrician checks the board has capacity before adding a circuit, because a charger on a full board is a design fault. Other countries use different voltages and rules.
- Enphase installer documentation centre Enphase Energy · Guide Lists EV charger, battery and gateway documents as an example of maker requirements
Surplus diversion: EV, immersion and heat pumpabout 2 hours
A diverter sends solar surplus to a useful load instead of exporting it, which needs correct sensing, settings and safety cut-outs.
A diverter senses export at the meter and varies power to a charger, an immersion heater or a heat pump, for instance heating a hot-water cylinder with surplus at noon. A diverter with no thermostat or cut-out is unsafe, and one that competes with the battery for the same surplus needs a priority order. Settings, wiring and safety cut-outs come from the maker's manual and local rules; immersion circuits need overheating protection. SMA's support hub lists energy-management apps and design tools as an example of maker support.
Load management and energy management systemsabout 2 hours
Load management limits the total of charging and other loads so the supply is not overloaded; the US code now names energy management systems.
The IAEI summary of the 2023 NEC says 705.13 was renamed Energy Management Systems, a sign that controlling loads and sources is now a design topic in its own right. A charger with no load control on a limited supply can trip the main fuse every evening. The practical need is the same elsewhere: where the supply cannot carry everything at once, something must decide, for instance by reducing charger power when an oven and a heat pump start together.
- 2023 NEC and photovoltaic power systems IAEI Magazine · Guide Summary of NEC 2023 changes to Articles 690, 705, 706 and 691
Export schemes and time-of-use tariffsabout 2 hours
Export payments and cheap-hour tariffs change what a battery or charger is worth, and the rules change often.
A payback sum should name the tariff and the date you read it, because a promise built on one rate may not survive next year's change. Time-of-use import tariffs make charging in cheap hours attractive for batteries and EVs, and rates and terms change, so read the current supplier terms. Ofgem's page says the Smart Export Guarantee requires some licensed suppliers to pay eligible small generators for exported electricity, based on export meter readings, at rates the supplier sets above zero; suppliers choose their own tariffs and terms.
- Smart Export Guarantee Ofgem (Great Britain) · Law or regulation
Grid-controlled devices and virtual power plantsabout 2 hours
Heat pumps, wallboxes and batteries can be controlled by the grid operator in return for lower fees, as Germany's section 14a shows.
Section 14a of the German Energy Industry Act covers controllable consumption devices, including heat pumps, non-public EV charging points, batteries and some others. A grid operator may control them in return for reduced grid fees, with control through a smart meter gateway where one exists. A virtual power plant is the wider idea of combining many such devices and controlling them together to help the grid; this roadmap lists no source on it. Where the law expects grid control, a charger that cannot accept it is the wrong product.
- EnWG section 14a: controllable consumption devices (in German) German federal law portal · Law or regulation German-language legal text; check the current wording
Practice task
Choose a fictional home with solar, a battery, an EV charger and a heat pump. Draw a one-page energy-flow diagram showing what each device does at noon on a sunny day and at 18:00 in winter, mark where a load manager would act, and list which parts are authorised-electrician work. Paper only; no live equipment is needed.
Skills you build
EV charger basicsLoad managementSurplus diversionTariff and export schemesControllable devices
Resources for this topic
Every source here is free. Each link opens the provider's own site in a new tab.
- Charging at home (Alternative Fuels Data Center) US Department of Energy · Guide US; Level 1 and Level 2, electrician installation, permits and NEC Article 625
- Electrical safety (topic index) HSE (United Kingdom) · Guide UK; index of free electrical safety guidance
- MCS: battery storage for your home MCS · Guide UK consumer page on the battery add-on that often accompanies solar and EV charging
Live Solar PV technician jobs
Roles whose title matches this career path.
Spot a problem with this topic?
Tell us what is wrong, missing or unclear here. Your note is attached to this topic.
Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.