Management of change and new equipment review
Management of change (MOC) means reviewing the safety and environmental effect of a change before it goes live. You will be able to run a review, set an end date on temporary changes and close the change out.
- Core
- Intermediate
- about 8 hours
Written by the GreenHired editorial teamSources last checked 20 November 2026How we research roadmaps
Is this a change, or a like-for-like replacement? That is the first of three questions to ask in order. The second is what the change could do, near it and far from it. The third is whether everything is ready before restart: the equipment as designed, the people trained, the documents updated. Then the change is closed out. The form matters less than the habit of asking before the work, not after.
A temporary alarm bypass
A tank has a high-level alarm. The sensor fails, the replacement is on order, and a supervisor asks to bypass the alarm until it arrives. This is an illustrative scenario, not advice for a real site.
The review first settles whether this is a change. It is: a bypass is not a replacement in kind, because the alarm no longer does its job. Next comes what it could do. The alarm protects against overfilling, so the review asks what else catches an overfill and how far the spill could travel, which may call for a fresh risk assessment or, on process plant, a structured hazard study.
The conditions follow. A compensating measure is named, such as someone checking the level at fixed times. The end date is tied to the sensor’s arrival. The person who authorises the bypass is named too, ideally someone who can say no. Everyone who fills the tank hears about it before the next fill, and the shift log records it. The isolations and permits for fitting the new sensor sit in safe systems of work.
Closing it out
The sensor goes in, the bypass comes out, someone tests the alarm and signs the form. If the end date passes first, the change is reviewed again, not quietly extended. That date is what stops a temporary change becoming permanent. HSE’s guidance also warns that too many changes at once get too little attention, so ask whether other changes are open on the same plant, and update the legal register if a change alters which rules apply.
People changes use the same form
Cutting a night crew from four to three looks like a rota decision. The review asks which tasks the missing person did: the round that checks a pump, the second pair of hands for a manual isolation. HSE says organisational changes are usually analysed less thoroughly than plant changes. Its CHIS7 sheet, listed in the resources, is written for major-hazard employers but works for any workplace.
What you will learn
- What counts as a change, and what is a replacement in kind.
- How to write a change review form that asks the right questions.
- How a pre-start-up review checks that the change matches its design.
- Why people and organisational changes need the same care as plant changes.
- How to train people, update procedures and close a change out.
The parts of this topic
Change triggersabout 1 hour
A change is anything that alters the plant, process, materials, procedures or the people controlling the hazards. Like-for-like replacements are treated differently.
The US process safety standard requires written procedures for changes to process chemicals, technology, equipment and procedures, and to facilities that affect a covered process, but excludes replacements in kind. HSE adds that organisational changes, such as cutting staffing, using contractors, outsourcing, combining departments or changing roles, are usually analysed less thoroughly than plant changes, yet can harm safety. A cheaper supplier of a solvent, for instance, is a change; an identical pump usually is not. Hardware is not the only thing that counts.
- Organisational change and transition management HSE (UK) · Guide
The review formabout 1 hour
The form asks for the technical basis, the effect on safety, health and environment, the procedures to change, the time the change will last and who authorises it.
A form that asks only 'is it safe?' gets a tick, not a review. The US standard lists five considerations before any change: the technical basis, the impact on safety and health, changes to operating procedures, the necessary time period and the authorisation requirements. HSE's technical guidance asks for a traceable safety, engineering and technical review covering process conditions, operating methods, engineering methods, safety, environmental conditions and hardware, then a risk assessment that includes fire, explosion and loss of containment. Consider the whole plant, because effects can be remote.
- Plant modification and change procedures HSE (UK) · Guide
Pre-start-up reviewabout 1 hour
Before a changed or new installation is used, check that it was built as designed, procedures are ready, earlier recommendations are resolved and people are trained.
Under the US standard, a pre-startup safety review is required for new facilities and for modified ones where the change requires updated process safety information. It confirms that construction and equipment match the design, that safety, operating, maintenance and emergency procedures are in place, that for a new facility the hazard-analysis recommendations are resolved or implemented, and that training is complete. A nearly empty punch list is not a reason to start up. In Great Britain, PUWER requires inspection after installation and before first use, and after reassembly at a new site.
- Inspection of work equipment (PUWER) HSE (UK) · Guide
Training and document updatesabout 1 hour
People affected by a change must be told and trained before start-up, and the procedures and drawings that describe the plant must be updated to match.
The US standard says employees who operate the process, and maintenance and contract employees whose tasks are affected, must be informed and trained in the change before start-up. Operating procedures and process safety information must be updated when a change alters them. Updating the drawing a month after start-up leaves operators working from the old one. In Great Britain, PUWER requires adequate training for anyone who uses work equipment, including supervisors and managers. Example: a new valve position changes the shutdown steps, so the procedure, the drawing and the operator briefing all change.
- Training and competence (PUWER) HSE (UK) · Guide
Temporary changes and close-outabout 1 hour
Temporary changes need an end date and a return plan. Every change ends with checks that it did what was intended and that records match reality.
OSHA's list of change considerations includes the necessary time period, which is where a temporary change gets its end date and its return-to-normal plan. HSE warns against too many simultaneous changes because some get too little attention, and advises phasing changes where possible and consulting staff before, during and after. HSE's technical guidance calls for accurate recording and monitoring of changes to plant and process. Close-out means checking the change worked, updating records and closing the form. Watch for a 'temporary' bypass that is still there two years later.
Practice task
Design a one-page management of change form and use it on an invented change, such as replacing a solvent with a cheaper one on a cleaning line. Complete every section, name who must review and approve, list the documents and training that must change before restart, and add a close-out checklist.
Skills you build
Management of changePre-start-up reviewOrganisational change riskDocument control
Resources for this topic
Every source here is free. Each link opens the provider's own site in a new tab.
- 29 CFR 1910.119: process safety management of highly hazardous chemicals OSHA (US) · Law or regulation Paragraph (l) covers management of change and (i) the pre-startup review.
- Process safety management guidelines (OSHA 3132) OSHA (US) · Guide Plain-language sections on management of change and pre-startup review.
- Organisational change and major accident hazards (CHIS7) HSE (UK) · Guide Written for major-hazard employers; useful for anyone managing people changes.
- Process safety management OSHA (US) · Guide
Latest Environmental Health & Safety jobs
No title matches the role right now, so these are the latest jobs in the same category.
No live jobs to show right now. Check back soon, or browse every green job.
Spot a problem with this topic?
Tell us what is wrong, missing or unclear here. Your note is attached to this topic.
Notes are sent from this page with JavaScript on. Without it, write to us on the contact page.